3.04 01 87 insulating finishing coatings. SNiP

INSULATING AND FINISHING COATINGS

Date of introduction 1988-07-01

1. GENERAL PROVISIONS

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidate of technical sciences N.N. Zavrazhin - topic leader, V.A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I.P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences D.K. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences, Prof. E.D. Belousov, Candidate of Technical Sciences G.S. Agadzhanov), SKTB Glavtunnelmetrostroy of the Ministry of Transport of the USSR (Candidate of Technical Sciences V.V. Krylova .

INTRODUCED BY TsNIIOMTP Gosstroy USSR.

PREPARED FOR APPROVAL by the Department of Standardization and Technical Standards in Construction of the USSR State Construction Committee (D.I. Prokofiev).

APPROVED by Decree of the State Construction Committee of the USSR dated December 4, 1987 No. 280.

With the entry into force of SNiP 3.04.01-87 “Insulating and finishing coatings”, SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72 are no longer valid; GOST 22753-77, GOST 22844-77, GOST 23305-78.

Complete drainage of water over the entire surface of the roofs should be carried out through external and internal drains without stagnation of water

The adhesion strength to the base and to each other of roofing and waterproofing carpet made from rolled materials over a continuous mastic adhesive layer of emulsion compositions with the base is not less than 0.5 MPa

Measuring, 5 measurements per 120-150 sq.m of coating surface (tapping should not change the nature of the sound); when the glued materials rupture, there should be no peeling of the mastic (the rupture should occur inside the rolled panel), acceptance certificate

The heat resistance and compositions of mastics for gluing rolled and slab materials, as well as the strength and compositions of adhesive layer solutions must correspond to the design. Deviations from the project - 5%.

Technical inspection, acceptance certificate

The location of panels and metal paintings (depending on the slope of the coating), their connection and protection in a regular coating, in places of abutments and interfaces in different planes must correspond to the project

Bubbles, swelling, air pockets, tears, dents, punctures, spongy structure, drips and sagging on the surface of roof coverings and insulation are not allowed

Increased humidity of bases, intermediate elements, coating and the entire structure compared to the standard

No more than 0.5%

Measuring, 5 measurements on an area of ​​50-70 sq.m of the coating surface or on individual areas of a smaller area in places identified by visual inspection, acceptance certificate

When accepting finished insulation and roofing, you must check:

correspondence of the number of reinforcing (additional) layers in mates (adjacents) to the project;

for waterproofing:

the quality of filling joints and holes in structures made of prefabricated elements with sealing materials;

quality of caulking;

correct waterproofing of bolt holes, as well as holes for injection of mortar for finishing structures;

absence of leaks and discontinuities of seam lines in metal waterproofing;

for roofs made of rolled materials, emulsion, mastic compositions:

the bowls of the water inlet funnel of internal drains should not protrude above the surface of the base;

the corners of adjoining structures (screeds and concrete) must be smooth and even, without sharp corners;

for roofs made of piece materials and roof parts made of metal sheets:

absence of visible gaps in the coating when inspecting the roof from the attic;

absence of chips and cracks (in asbestos-cement and sealed flat and corrugated sheets);

in places identified by continuous visual inspection, work log

Permissible thickness of each layer when installing multilayer plasters without polymer additives, mm:

Measuring, at least 5 measurements per 70-100 sq.m of coating surface or in one room of a smaller area in places identified by continuous

spray on stone, brick, concrete surfaces - up to 5

visual inspection, work log

soil from lime, lime-gypsum solutions - up to 7

covering layer of plaster coating - up to 2

PRODUCTION OF PAINTING WORKS

Technical, all junctions, work log

The end surfaces of the laid section of monolithic screeds, after removing the beacon or limiting slats, before laying the mixture in the adjacent section of the screed, must be primed (see clause 4.11) or moistened (see clause 4.12), and the working seam should be smoothed so that it is invisible

Visual, at least four times per shift, work log

Smoothing the surface of monolithic screeds should be carried out under coatings on mastics and adhesive layers and under continuous (seamless) polymer coatings before the mixtures set

The same, the entire surface of the screeds, work log

Sealing the joints of prefabricated screeds made of fibreboards should be done along the entire length of the joints with strips of thick paper or adhesive tape 40 - 60 mm wide

Technical, all joints, work log

Laying of additional elements between prefabricated screeds on cement and gypsum binders should be done with a gap of 10-15 mm wide, filled with a mixture similar to the screed material. If the width of the gaps between the prefabricated screed slabs and walls or partitions is less than 0.4 m, the mixture must be laid over a continuous soundproofing layer

Technical, all clearances, work log

WATERPROOFING DEVICE

4.21. Pasted waterproofing using bitumen, tar and mastics based on them should be carried out in accordance with Section. 2, and polymer waterproofing - in accordance with SNiP 3.04.03-85.

4.22. Waterproofing from crushed stone impregnated with bitumen should be carried out in accordance with SNiP 3.06.03-85.

CONSTRUCTION OF WOOD COATINGS
AND PRODUCTS BASED ON IT

4.34. All boards of the plank covering must be attached to each joist with nails 2-2.5 times longer than the thickness of the covering, and parquet panels - with nails 50-60 mm long. Nails should be driven obliquely into the face of the plank boards /.*`kb(o) and into the base of the bottom cheek of the groove on the edges of parquet boards and parquet panels with the heads embedded. Driving nails into the front surface of parquet boards and parquet panels is prohibited.

4.35. The joints of the ends of the boards of plank coverings, the joints of the ends and side edges with the ends of adjacent parquet boards, as well as the joints of the edges of adjacent parquet panels parallel to the joists should be placed on the joists.

4.37. Super-hard fibreboards, stacked and block parquet should be glued to the base with quick-hardening mastics on water-resistant binders, used in a cold or heated state. Adhesive mastic on the base under super-hard fibreboards should be applied in strips 100-200 mm wide along the perimeter of the boards and in the middle zone with an interval of 300-400 mm. When laying out and cutting wood fiber boards, joining the four corners of the boards at one point is not allowed. 4.38. When installing coatings made of wood and products based on them, it is necessary to comply with the requirements of Table.

Technical requirements

Maximum deviations, mm

All logs, boards (except for the front side), wooden spacers laid on posts under the logs, as well as wood under the base of fiberboards must be antiseptic

Visual, all materials, inspection report of hidden work

The moisture content of materials should not exceed:

Measuring, at least three dimensions

logs and gaskets

for every 50-70 sq.m

covering and base boards

floor surfaces,

Installation of insulation dispersedly reinforced with glass fiber (fiberglass fibres):

fiber sizes - 20 mm

The ratio by weight of aluminous cement to Portland cement is 90: 10

Measuring, periodic at least 16 measurements per shift (every 0.5 hours of work), work log

Heavy concrete for constructing roofs without an insulating coating (roof) must contain:

plasticizing and air-entraining additives, fillers made of fractionated sand and coarse-grained crushed stone;

Portland cement - hydrophobic, containing no more than 6% calcium aluminate;

crushed stone of igneous rocks or gravel with a temporary resistance of at least 100 MPa in a water-saturated state; granulometric composition of crushed stone, mm:

sand protective layer size modulus - 2.1 - 3.15

Measuring, periodic, at least 4 times per shift, work log

Gravel and other frost-resistant mineral materials should be sorted and washed

PREPARATION OF FOUNDATIONS AND UNDERLYING

INSULATION ELEMENTS

2.4. Dust removal of substrates must be carried out before applying primers and insulating compounds, including adhesive adhesives and mastics.

2.5. Leveling screeds (from cement-sand, gypsum, gypsum-sand mortars and asphalt concrete mixtures) should be arranged with grips 2-3 m wide along guides with leveling and compacting the surface.

2.6. The surface priming before applying adhesive and insulating compounds must be continuous without gaps or breaks. Priming of screeds made from cement-sand mortars should be done no later than 4 hours after their installation, using primers based on slowly evaporating solvents (with the exception of screeds with a surface slope of more than 5%, when priming should be done after they have hardened). When preparing the base surface, it is necessary to comply with the requirements of Table. 2.

The primer must have strong adhesion to the base, and there should be no traces of binder left on the tampon attached to it.

table 2

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible deviations in the surface of the base for roll and non-roll emulsion and mastic insulation and roofing:

along the slope and on a horizontal surface

across the slope and on a vertical surface

from piece materials:

along and across the slope

Measuring, technical inspection, at least 5 measurements for every 70-100 m2 of surface or on a smaller area in places determined by visual inspection

Deviations of the element plane from a given slope (over the entire area)

Thickness of the structural element (from design)

Number of irregularities (smooth outline with a length of no more than 150 mm) on a surface area of ​​4 m2

No more than 2

Primer thickness, mm:

for roofs made of fused materials - 0.7

when priming a hardened screed - 0.3

when priming screeds within 4 hours after applying the solution - 0.6

2.7. The humidity of the base before applying the primer should not exceed the values ​​​​indicated in the table. 3. Only water-based primers or insulating compounds may be applied to wet substrates if the moisture appearing on the surface of the substrate does not violate the integrity of the coating film.

2.8. Metal surfaces of pipelines, equipment and fasteners to be insulated must be cleaned of rust, and those subject to anti-corrosion protection must be treated in accordance with the design.

2.9. Insulation of installed equipment and pipelines should be carried out after they are permanently secured in the designed position. Thermal insulation of equipment and pipelines in places that are difficult to reach for insulation must be carried out completely before installation, including the installation of cover shells.

Insulation of pipelines located in non-passing channels and trays must be performed before they are installed in the channels.

2.10. Equipment and pipelines filled with substances must be cleared of them before insulation work begins.

2.11. When working in sub-zero temperatures, rolled insulation materials must be heated to a temperature of at least 15 ° C within 20 hours, rewound and delivered to the installation site in an insulated container.

THERMAL INSULATION DEVICE FROM PLATES AND BULK MATERIALS

Before sending an electronic appeal to the Ministry of Construction of Russia, please read the rules of operation of this interactive service set out below.

1. Electronic applications within the sphere of competence of the Ministry of Construction of Russia, filled out in accordance with the attached form, are accepted for consideration.

2. An electronic appeal may contain a statement, complaint, proposal or request.

3. Electronic appeals sent through the official Internet portal of the Ministry of Construction of Russia are submitted for consideration to the department for working with citizens' appeals. The Ministry ensures objective, comprehensive and timely consideration of applications. Review of electronic appeals is free of charge.

4. In accordance with Federal Law No. 59-FZ dated May 2, 2006 “On the procedure for considering appeals from citizens of the Russian Federation,” electronic appeals are registered within three days and sent, depending on the content, to the structural divisions of the Ministry. The appeal is considered within 30 days from the date of registration. An electronic appeal containing issues the solution of which is not within the competence of the Ministry of Construction of Russia is sent within seven days from the date of registration to the relevant body or the relevant official whose competence includes resolving the issues raised in the appeal, with notification of this to the citizen who sent the appeal.

5. Electronic appeal is not considered if:
- absence of the applicant’s surname and name;
- indication of an incomplete or unreliable postal address;
- the presence of obscene or offensive expressions in the text;
- the presence in the text of a threat to the life, health and property of an official, as well as members of his family;
- using a non-Cyrillic keyboard layout or only capital letters when typing;
- absence of punctuation marks in the text, presence of incomprehensible abbreviations;
- the presence in the text of a question to which the applicant has already been given a written answer on the merits in connection with previously sent appeals.

6. The response to the applicant is sent to the postal address specified when filling out the form.

7. When considering an appeal, disclosure of information contained in the appeal, as well as information relating to the private life of a citizen, is not permitted without his consent. Information about applicants’ personal data is stored and processed in compliance with the requirements of Russian legislation on personal data.

8. Appeals received through the site are summarized and presented to the leadership of the Ministry for information. Answers to the most frequently asked questions are periodically published in the sections “for residents” and “for specialists”

BUILDING REGULATIONS

INSULATING AND FINISHING COATINGS

SNiP 3.04.01-87

STATE CONSTRUCTION COMMITTEE OF THE USSR

Moscow 1988

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidate of technical sciences N. N. Zavrazhin - topic leader, V. A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I. P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences D K. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences Prof. E. D. Belousov, Candidate of Technical Sciences G. S. Agadzhanov), SKTB Glavtunnelmetrostroy Ministry of Transport Construction of the USSR (Candidates of Technical Sciences V. V. Krylova, V. A. G. Golubova), Office of the Soyuzmetrospetsstroy Ministry of Transport and Construction of the USSR (A. P. Levina, P. F. Litvina), Research Institute of Reinforced Concrete Structures of the State Committee for Construction of the USSR (Doctor of Technical Sciences, Prof. F. M. Ivanova).

INTRODUCED BY TsNIIOMTP Gosstroy USSR.

PREPARED FOR APPROVAL by the Department of Standardization and Technical Standards in Construction of the USSR State Construction Committee (D.I. Prokofiev).

With the entry into force of SNiP 3.04.01-87 “Insulating and finishing coatings”, SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72 are no longer valid; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using a regulatory document, one should take into account the approved changes to building codes and regulations and state standards published in the journal “Bulletin of Construction Equipment”, “Collection of Amendments to Construction Codes and Rules” of the USSR State Construction Committee and the information index “USSR State Standards” of the USSR State Standard.


1. GENERAL PROVISIONS

1.1. These building codes and regulations apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to the special operating conditions of buildings and structures.

1.2. Insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - according to the standard). Replacement of materials, products and compositions provided for by the project is allowed only by agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can begin only after the execution of an act (permit) signed by the customer, representatives of the installation organization and the organization performing thermal insulation work.

1.4. The installation of each insulation element (roof), floor, protective and finishing coatings should be carried out after checking the correct execution of the corresponding underlying element and drawing up an inspection report for hidden work.

1.5. With appropriate justification, in agreement with the customer and the design organization, it is allowed to prescribe methods for performing work and organizational and technological solutions, as well as establish methods, volumes and types of registration of quality control of work that differ from those provided for in these rules.


SNiP 3.04.01-87

BUILDING REGULATIONS

INSULATING AND FINISHING COATINGS

Date of introduction 1988-07-01

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidate of technical sciences N.N. Zavrazhin - topic leader, V.A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I.P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences D.K. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences, Prof. E.D. Belousov, Candidate of Technical Sciences G.S. Agadzhanov), SKTB Glavtunnelmetrostroy of the Ministry of Transport of the USSR (Candidate of Technical Sciences V.V. Krylova .

INTRODUCED BY TsNIIOMTP Gosstroy USSR.

PREPARED FOR APPROVAL by the Department of Standardization and Technical Standards in Construction of the USSR State Construction Committee (D.I. Prokofiev).

APPROVED by Decree of the State Construction Committee of the USSR dated December 4, 1987 No. 280.

With the entry into force of SNiP 3.04.01-87 “Insulating and finishing coatings”, SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72 are no longer valid; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using a regulatory document, you should take into account the approved changes to building codes and regulations and state standards published in the journal "Bulletin of Construction Equipment", "Collection of Amendments to Construction Codes and Rules" of the USSR State Construction Committee and the information index "USSR State Standards" of the USSR State Standard.

1. GENERAL PROVISIONS

1.1. These building codes and regulations apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to the special operating conditions of buildings and structures.

1.2. Insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - according to the standard). Replacement of materials, products and compositions provided for by the project is allowed only by agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can begin only after the execution of an act (permit) signed by the customer, representatives of the installation organization and the organization performing thermal insulation work.

1.4. The installation of each insulation element (roof), floor, protective and finishing coatings should be carried out after checking the correct execution of the corresponding underlying element and drawing up an inspection report for hidden work.

1.5. With appropriate justification, in agreement with the customer and the design organization, it is allowed to prescribe methods for performing work and organizational and technological solutions, as well as establish methods, volumes and types of registration of quality control of work that differ from those provided for in these rules.

2. INSULATING COATINGS AND ROOFINGS

GENERAL REQUIREMENTS

2.1. Insulation and roofing work can be carried out from 60 to minus 30 °C in the environment (work using hot mastics - at an ambient temperature of at least minus 20 °C, using water-based compounds without antifreeze additives at least 5 °C).

2.2. In the foundations for roofing and insulation, in accordance with the project, the following work must be performed:

seal the seams between prefabricated slabs;

arrange temperature-shrinkable seams;

install embedded elements;

plaster sections of vertical surfaces of stone structures to the height of the junction of the rolled or emulsion-mastic roofing carpet and insulation.

2.3. Insulating compounds and materials must be applied in continuous and uniform layers or in one layer without gaps or sagging. Each layer must be laid on the hardened surface of the previous one, leveling the applied compounds, with the exception of paint ones. When preparing and preparing insulating compositions, the requirements of Table. 1.

Table 1

Technical requirements

Limit deviations

Bitumen and tar (pitch) must be used cleaned of impurities and dehydrated. Heating should not exceed, °C:

Measuring, periodic at least 4 times per shift, work log

bitumen - 180

tar (pitch) - 140

Fillers (aggregates) must be sifted through a sieve with cell sizes, mm:

for sand - 1.5

for dusty ones - 2

for fibrous - 4

Permissible moisture content of fillers (aggregates):

for sand

for compositions with sealing additives

for other compounds

Temperature of emulsions and their components, °C:

The same, at least 5-6 times per shift, work log

bitumen - 110

emulsifier solution - 90

latex (when introduced into the emulsion) - 70

Minus 10 °C

Uniformity of bitumen distribution in bitumen perlite and bitumen expanded clay - 90%

The compaction coefficient of bitumen perlite and bitumen expanded clay under pressure of 0.67-0.7 MPa is not less than 1.6

Temperature when applying mastics, °C:

hot bitumen - 160

hot tar - 130

cold (in winter) - 65

Construction of insulation coatings dispersedly reinforced with glass fiber (fiberglass fibres):

Measuring, periodic at least 16 measurements per shift (every 0.5 hours of work), work log

fiber sizes - 20 mm

The ratio by weight of aluminous cement to Portland cement is 90: 10

Heavy concrete for constructing roofs without an insulating coating (roof) must contain:

Measuring, periodic, at least 4 times per shift, work log

plasticizing and air-entraining additives, fillers made of fractionated sand and coarse crushed stone;

Portland cement - hydrophobic, containing no more than 6% calcium aluminate;

crushed stone of igneous rocks or gravel with a temporary resistance of at least 100 MPa in a water-saturated state; granulometric composition of crushed stone, mm:

sand protective layer size modulus - 2.1 - 3.15

Gravel and other frost-resistant mineral materials should be sorted and washed

PREPARATION OF BASES AND UNDERLYING INSULATION ELEMENTS

2.4. Dust removal of substrates must be carried out before applying primers and insulating compounds, including adhesive adhesives and mastics.

2.5. Leveling screeds (from cement-sand, gypsum, gypsum-sand mortars and asphalt concrete mixtures) should be arranged with grips 2-3 m wide along guides with leveling and compacting the surface.

2.6. The surface priming before applying adhesive and insulating compounds must be continuous without gaps or breaks. Priming of screeds made from cement-sand mortars should be done no later than 4 hours after their installation, using primers based on slowly evaporating solvents (with the exception of screeds with a surface slope of more than 5%, when priming should be done after they have hardened). When preparing the base surface, it is necessary to comply with the requirements of Table. 2.

The primer must have strong adhesion to the base, and there should be no traces of binder left on the tampon attached to it.

table 2

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible deviations of the base surface for roll and non-roll emulsion and mastic insulation and roofing:

Measuring, technical inspection, at least 5 measurements for every 70-100 sq.m of surface or on a smaller area in places determined by visual inspection

along a slope and on a horizontal surface

across a slope and on a vertical surface

from piece materials:

along and across the slope

Deviations of the element plane from a given slope (over the entire area)

Thickness of the structural element (from design)

Number of irregularities (smooth outline with a length of no more than 150 mm) on a surface area of ​​4 sq.m.

No more than 2

Primer thickness, mm:

for roofs made of fused materials - 0.7

when priming a hardened screed - 0.3

when priming screeds within 4 hours after applying the solution - 0.6

2.7. The humidity of the base before applying the primer should not exceed the values ​​​​indicated in the table. 3. Only water-based primers or insulating compounds may be applied to wet substrates if the moisture appearing on the surface of the substrate does not violate the integrity of the coating film.

2.8. Metal surfaces of pipelines, equipment and fasteners to be insulated must be cleaned of rust, and those subject to anti-corrosion protection must be treated in accordance with the design.

2.9. Insulation of installed equipment and pipelines should be carried out after they are permanently secured in the designed position. Thermal insulation of equipment and pipelines in places that are difficult to reach for insulation must be carried out completely before installation, including the installation of cover shells.

Insulation of pipelines located in non-passing channels and trays must be performed before they are installed in the channels.

2.10. Equipment and pipelines filled with substances must be cleared of them before insulation work begins.

2.11. When working in sub-zero temperatures, rolled insulating materials must be heated to a temperature of at least 15 °C within 20 hours, rewound and delivered to the installation site in an insulated container.

2.12. When insulating roofs from large-sized complex panels with a factory-applied roofing carpet, sealing the joints of the roof panels and gluing them must be done after checking the insulation of the mounted panels.

INSULATION AND ROOFING FROM ROLL MATERIALS

2.13. Roofing and waterproofing carpets made of rolled materials with a mastic layer pre-fused at the factory must be glued onto a pre-primed base by melting or liquefying (plasticizing) the mastic layer of the material without the use of adhesive mastics. The adhesive strength must be at least 0.5 MPa.

Liquefaction of the mastic layer must be carried out at an air temperature of at least 5 ° C with the simultaneous laying of the rolled carpet or before its laying (depending on the ambient temperature).

Melting of the mastic layer should be carried out simultaneously with the laying out of the panels (temperature of the molten mastic is 140-160 ° C). Each laid roof layer must be rolled with a roller before installing the next one.

2.14. Before sticking, roll materials must be marked at the place of installation; The layout of the panels of rolled materials must ensure that their overlap values ​​are observed when gluing.

In accordance with the design, the mastic must be applied in a uniform continuous layer, without gaps or in a stripe layer. When spot gluing panels to the base, mastic should be applied after rolling out the panels at the locations of the holes.

2.15. When installing roll insulation or roofing using adhesives, hot mastics should be applied to the primed base immediately before gluing the panels. Cold mastics (glues) should be applied to the base or panel in advance. Between applying the adhesive compositions and gluing the panels, it is necessary to observe technological breaks to ensure strong adhesion of the adhesive compositions to the base.

Each layer should be laid after the mastics have hardened and achieved strong adhesion to the base of the previous layer.

2.16. When installing roofs, sheets of rolled materials should be glued:

in the direction from low areas to high ones with the panels located along the length perpendicular to the water flow with roof slopes of up to 15%;

in the direction of drainage - with roof slopes of more than 15%.

Cross-sticking of insulation panels and roofing is not allowed. The type of roll carpet sticker (solid, striped or dotted) must correspond to the project.

2.17. When gluing, the insulation and roof panels must be overlapped by 100 mm (70 mm across the width of the panels of the lower layers of the roof of roofs with a slope of more than 1.5%).

2.18. When installing insulation or roofing, fiberglass fabric must be spread, laid without creating waves, immediately after applying hot mastic and covered with mastic with a thickness of at least 2 mm.

Subsequent layers should be laid similarly after the mastic of the lower layer has cooled.

2.19. Temperature-shrinkage seams in screeds and joints between coating slabs must be covered with strips of rolled material up to 150 mm wide and glued to one side of the seam (joint).

2.20. In places adjacent to protruding roof surfaces (parapets, pipelines, etc.), the roofing carpet must be raised to the top of the screed side, glued with mastic and putty on the upper horizontal seams. Gluing additional layers of roofing should be done after installing the top layer of the roof, immediately after applying the adhesive mastic in a continuous layer.

2.21. When gluing panels of roofing carpet along the roof slope, the upper part of the panel of the lower layer must overlap the opposite slope by at least 1000 mm. The mastic should be applied directly under the rolled roll in three strips 80-100 mm wide. Subsequent layers must be glued on a continuous layer of mastic.

When gluing panels across the roof slope, the upper part of the panel of each layer laid on the ridge should overlap the opposite roof slope by 250 mm and be glued to a continuous layer of mastic.

2.22. When installing a protective gravel coating on the roofing carpet, it is necessary to apply hot mastic in a continuous layer 2 - 3 mm thick and 2 m wide, immediately scattering over it a continuous layer of gravel, cleared of dust, 5-10 mm thick. The number of layers and total thickness of the protective coating must correspond to the design.

2.23. When installing roll insulation and roofing, it is necessary to comply with the requirements of Table. 3.

Table 3

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The permissible moisture content of the substrates when applying all compositions, except for water-based compositions, should not exceed:

Measuring, technical inspection, at least 5 measurements evenly for every 50-70 sq.m of base, registration

concrete

cement-sand, gypsum and gypsum-sand

any bases when applying water-based compounds

Before surface moisture appears

Temperature when applying hot mastics, °C:

Measuring, periodic, at least 4 times per shift, work log

bitumen - 160

tar - 130

Thickness of the mastic layer when gluing a rolled carpet, mm:

hot bitumen - 2.0

intermediate layers - 1.5

cold bitumen - 0.8

Thickness of one insulation layer, mm:

Measuring, technical inspection, at least 5 measurements for every 70-100 sq.m in places determined by visual inspection, work log

cold asphalt mastics - 7

cement mortars - 10 emulsions - 3

polymer compositions (such as "Krovlelit" and "Venta") - 1

INSULATION AND ROOFING DEVICE FROM POLYMER AND EMULSION-BITUMEN COMPOSITIONS

2.24. When installing insulation and roofs made from emulsion-mastic compositions, each layer of the insulating carpet must be applied continuously, without breaks, of uniform thickness after the primer or bottom layer has hardened.

2.25. When installing insulation and roofing from polymer compositions such as "Krovlelit" and "Venta", they must be applied with high-pressure units that ensure density, uniform thickness of the coating and adhesion strength of the coating to the base of at least 0.5 MPa. When using cold asphalt emulsion mastics, the supply and application of the compositions should be carried out by units with screw pumps (mechanical action), ensuring the adhesion strength of the coating to the base of at least 0.4 MPa.

2.26. When installing insulation and roofing from emulsion-mastic compositions reinforced with fiberglass fibers, their application should be carried out with units that ensure the production of fibers of the same length, uniform distribution in the composition and density of the insulating coating.

2.27. When installing insulation and roofing made of polymer and emulsion-mastic compositions, the requirements of Table 1 must be met. 3. Roof junctions should be arranged similarly to the installation of roll roofs.

INSULATION DEVICE FROM CEMENT SOLUTIONS, HOT ASPHALT MIXTURES, BITUMEN-PERLITE AND BITUMEN-CERAMZITE

2.28. Bitumen perlite, bitumen expanded clay, cement mortars, hot asphalt mixtures with a surface slope of up to 25% must be laid along lighthouse slats in strips 2-6 m wide in layers of uniform thickness (no more than 75 mm) with compaction and smoothing of the layer surface.

Each layer must be laid after the previous one has hardened.

2.29. When installing cement waterproofing from mortars using waterproof expanding cements (WRC), waterproof non-shrinking cements (WBC) or Portland cement with compacting additives, the compositions should be applied to the base surface wetted with water.

Each subsequent layer must be applied no later than 30 minutes (when using VRC and VBC compositions) or no more than 24 hours (when using Portland cement compositions with sealing additives) after hardening of the previous layer.

Cement waterproofing must be protected from mechanical influences for two days after application (1 hour when using VBC and VRC).

2.30 Moistening of cement waterproofing during hardening should be carried out with a sprayed stream of water without pressure when using the following compositions:

VRC and VBC - 1 hour after application and every 3 hours during the day;

on Portland cement with sealing additives - 8-12 hours after application, and then 2-3 times a day for 14 days.

2.31. When installing insulation from bitumen perlite, bitumen expanded clay, waterproofing from cement mortars and hot asphalt mixtures, mastics and bitumens, it is necessary to comply with the requirements of Table 4.

Table 4

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible surface deviations (when checked with a two-meter rod):

Measuring, at least 5 measurements for every 50 - 100 sq.m of surface or on a smaller area in places determined by visual inspection

horizontally

vertically

element plane from a given slope - 0.2%

No more than 150 mm

coating element thickness -5...+10%

No more than 3.0 mm

Mobility of compositions (mixtures) without plasticizers, cm:

Measuring, at least 3 measurements for every 70-100 sq.m of coating surface

when applied manually - 10

when applied by installations with piston or screw pumps - 5

when using plasticizers - 10

The temperature of hot asphalt mixtures, bitumen perlite and bitumen expanded clay during application is at least 120 ° C

Measuring, periodic, at least 8 times per shift, work log

PRODUCTION OF THERMAL INSULATION WORKS USING SOFT, HARD AND SEMI-HARD FIBER PRODUCTS AND CONSTRUCTION OF THERMAL INSULATION COVERS FROM HARD MATERIALS

2.32. When constructing cover shells from flat or corrugated asbestos-cement sheets, their installation and fastening must comply with the design.

When constructing thermal insulation cover shells made of rigid and flexible (non-metallic) materials, it is necessary to ensure a tight fit of the shells to the thermal insulation with reliable fastening using fasteners and thorough sealing of the joints of flexible shells with their gluing in accordance with the design.

On pipelines with a diameter of up to 200 mm, fiberglass should be laid spirally, on pipelines with a diameter of more than 200 mm - in separate panels in accordance with the requirements of the project.

2.33. Installation of thermal insulation structures and cover shells must begin from unloading devices, flange connections, curved sections (bends) and fittings (tees, crosses) and be carried out in the direction opposite to the slope, and on vertical surfaces - from bottom to top.

2.34. When installing thermal insulation from rigid products laid dry, a gap of no more than 2 mm must be provided between the products and the insulated surface.

When gluing hard products, the temperature of the mastics must meet the requirements of Table. 3.

Fastening of products to the base must correspond to the project.

2.35. When installing thermal insulation of pipelines using soft and semi-rigid fibrous products, it is necessary to ensure:

compaction of thermal insulation materials according to the project with a compaction coefficient for soft fibrous products of no more than 1.5, for semi-rigid ones - 1.2;

tight fit of products to the insulated surface and to each other;

when insulating in several layers - overlap longitudinal and transverse seams;

dense spiral laying of insulation with cords and bundles with minimal deviation relative to the plane perpendicular to the axis of the pipeline, and winding in multilayer structures of each subsequent layer in the direction opposite to the turns of the previous layer;

installation of fasteners on horizontal pipelines and devices to prevent sagging of thermal insulation.

THERMAL INSULATION DEVICE FROM PLATES AND BULK MATERIALS

2.36. When installing thermal insulation from slabs, insulation materials must be laid on the base tightly to each other and have the same thickness in each layer.

When installing thermal insulation in several layers, the seams of the slabs must be spaced apart.

2.37. Thermal insulation bulk materials must be sorted into fractions before installation. Thermal insulation must be installed along lighthouse slats in strips 3-4 m wide with loose insulation of smaller fractions laid in the lower layer.

Layers should be laid with a thickness of no more than 60 mm and compacted after laying.

2.38. When installing thermal insulation from slabs and bulk materials, the requirements of Table. 5 and 6.

Table 5

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The permissible moisture content of the bases should not exceed:

Measuring, at least 5 measurements for every 50-70 sq.m of coating surface, work log

from prefabricated

from monolithic

Thermal insulation made from piece materials, the thickness of the interlayer layer should not exceed, mm:

from adhesives and cold mastics - 0.8

from hot mastics - 1.5

width of joints between slabs, blocks, products, mm:

when sticking - no more than 5 (for hard products - 3)

when laying dry - no more than 2

Monolithic and slab thermal insulation: thickness of insulation coating (from design)

5...+10%, but not more than 20 mm

Deviations of the insulation plane:

Measuring, for every 50-100 sq.m of coating surface

from a given slope

horizontally

vertically

The size of the ledges between tiles and roofing sheets should not exceed 5 mm

The amount of overlap of slabs and sheets must correspond to the design - 5%

Table 6

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Deviations of insulation thickness from the design

Measuring, at least 3 measurements for every 70-100 sq.m of coating surface after a complete visual inspection, work log

Deviations of the compaction coefficient from the design

The same, at least 5 measurements for every 100-150 sq.m of coating surface

CONSTRUCTION OF ROOFS FROM PIECES MATERIALS

2.39. When installing wooden foundations (lathing) under roofs made of piece materials, the following requirements must be observed:

the joints of the sheathing should be spaced apart;

the distances between the sheathing elements must correspond to the design ones;

in places where eaves overhangs, valleys and valleys are covered, as well as under roofs made of small-piece elements, the foundations must be made of boards (solid).

2.40. Piece roofing materials should be laid on the sheathing in rows from the eaves to the ridge according to preliminary markings. Each overlying row must overlap the underlying one.

2.41. Corrugated asbestos-cement sheets of ordinary profile and medium-wavy must be laid offset by one wave in relation to the sheets of the previous row or without offset. Sheets of reinforced and unified profiles must be laid in relation to the sheets of the previous row without displacement.

When laying sheets without displacement on a wave at the junction of four sheets, the corners of the two middle sheets should be trimmed with a gap between the joining corners of the VO sheets of 3-4 mm and the SV, UV and VU sheets of 8-10 mm.

2.42. Asbestos-cement sheets VO and SV should be fastened to the sheathing with slate nails with a galvanized head, HC and VU sheets with screws with special grips, flat sheets - with two nails and an anti-wind button, outer sheets and ridge parts - in addition with two anti-wind brackets.

2.43. When installing roofs made of piece materials, the requirements of Table. 4.

INSULATION AND ROOF DETAILS FROM METAL SHEETS

2.44. Metal waterproofing must be installed by welding sheets in accordance with the project. After welding, the filling of the cavities behind the insulation should be injected with a composition under a pressure of 0.2-0.3 MPa.

2.45. When installing metal roofs, parts and junctions from metal sheets of any type of roof, the connection of paintings located along the water drainage must be carried out using lying seams, except for ribs, slopes and ridges, where the paintings must be connected with standing seams. For roof slopes of less than 30°, the rebated seam should be made double and coated with red lead putty. The amount of folding of the paintings for the installation of recumbent folds should be taken as 15 mm; standing seams -20 mm for one and 35 mm for another adjacent picture.

The paintings must be secured to the base with clamps passed between the folds of the sheets and T-shaped crutches.

REQUIREMENTS FOR READY INSULATION (ROOF) COATINGS AND STRUCTURAL ELEMENTS

2.46. The requirements for finished insulating (roofing) coverings and structures are given in Table. 7.

Table 7

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Complete drainage of water over the entire surface of the roofs should be carried out through external and internal drains without stagnation of water

The adhesion strength to the base and to each other of roofing and waterproofing carpet made from rolled materials over a continuous mastic adhesive layer of emulsion compositions with the base is not less than 0.5 MPa

Measuring, 5 measurements per 120-150 sq.m of coating surface (tapping should not change the nature of the sound); when the glued materials rupture, there should be no peeling of the mastic (the rupture should occur inside the rolled panel), acceptance certificate

The heat resistance and compositions of mastics for gluing rolled and slab materials, as well as the strength and compositions of adhesive layer solutions must correspond to the design. Deviations from the project - 5%.

Technical inspection, acceptance certificate

The location of panels and metal paintings (depending on the slope of the coating), their connection and protection in a regular coating, in places of abutments and interfaces in different planes must correspond to the project

Bubbles, swelling, air pockets, tears, dents, punctures, spongy structure, drips and sagging on the surface of roof coverings and insulation are not allowed

Increased humidity of bases, intermediate elements, coating and the entire structure compared to the standard

No more than 0.5%

Measuring, 5 measurements on an area of ​​50-70 sq.m of the coating surface or on individual areas of a smaller area in places identified by visual inspection, acceptance certificate

When accepting finished insulation and roofing, it is necessary to check: the compliance of the number of reinforcing (additional) layers in the interfaces (adjacents) with the project; for waterproofing: the quality of filling joints and holes in structures made of prefabricated elements with sealing materials; quality of caulking; correct waterproofing of bolt holes, as well as holes for injection of mortar for finishing structures; absence of leaks and discontinuities of seam lines in metal waterproofing; for roofs made of rolled materials, emulsion, mastic compositions: the bowls of the water inlet funnel of internal drains should not protrude above the surface of the base; the corners of adjoining structures (screeds and concrete) must be smooth and even, without sharp corners; for roofs made of piece materials and roof parts made of metal sheets: absence of visible gaps in the coating when inspecting the roof from the attic; absence of chips and cracks (in asbestos-cement and sealed flat and corrugated sheets); strong connection of drainpipe links to each other; the presence of smearing of double lying folds in the joints of metal paintings on a coating with a slope of less than 30°; for thermal insulation: continuity of layers, quality of lining of places where pipelines, equipment, structural parts pass through, etc. through thermal insulation; absence of mechanical damage, sagging layers and loose fit to the base

Deviations from the project are not allowed

Technical inspection, acceptance certificate

3. FINISHING WORKS AND PROTECTION OF BUILDING STRUCTURES AND TECHNOLOGICAL EQUIPMENT FROM CORROSION (ANTI-CORROSION WORK)

GENERAL PROVISIONS

3.1. Finishing work, with the exception of finishing facades, must be carried out at a positive ambient temperature and the surfaces being finished are not lower than 10 ° C and air humidity is not more than 60%. This temperature in the room must be maintained around the clock, no less than 2 days before the start and 12 days after the completion of work, and for wallpaper work - before the facility is put into operation.

3.2. Work on applying protective coatings should be carried out at a temperature of the ambient air and protected surfaces not lower than, °C:

10 - for paint and varnish protective coatings made from compositions prepared on the basis of natural resins; mastic and putty coatings made of silicate compounds; adhesive protective coatings using bitumen roll materials, polyisobutylene plates, Butylkor-S plates, duplicated polyethylene; rubber coatings; facing and lining coatings using acid-resistant silicate putties and mastics such as "Bituminol"; for acid-resistant concrete and silicate polymer concrete;

15 - for paint and varnish reinforced and non-reinforced continuous coatings from compositions prepared on the basis of synthetic resins; mastic coatings and sealants made from compounds based on synthetic rubbers and nairite; coatings made of sheet polymer materials; facing and lining coatings using putties such as "Arzamit", "Furankor", as well as polyester, epoxy resins and resins with epoxy additives; for coatings made of polymer concrete and polymer cement coatings;

25 - for coatings made from Polan.

3.3. Finishing work must be carried out in accordance with the work project (WPP) for the construction of buildings and structures. Before finishing work begins, the following work must be completed:

the premises being finished are protected from precipitation;

waterproofing, heat and sound insulation and leveling floor screeds were installed;

the seams between the blocks and panels are sealed;

the joints of window, door and balcony blocks are sealed and insulated;

glazed light openings;

embedded products were installed, heat and water supply and heating systems were tested.

Plastering and cladding (according to the project) of surfaces in places where embedded products of sanitary systems are installed must be performed before the start of their installation.

3.4. Before finishing the facades, the following work must additionally be completed:

external waterproofing and roofing with details and connections;

installation of all floor structures on balconies;

installation and fastening of all metal paintings edging architectural details on the facade of the building;

installation of all fastening devices for drainpipes (according to the project).

3.5. Anti-corrosion work should be carried out in accordance with the requirements of SNiP 3.04.03-85 “Protection of building structures and structures from corrosion”.

3.6. When preparing and preparing finishing and anti-corrosion compounds, it is necessary to comply with the requirements of Table. 8.

Table 8

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Plastering solutions must pass without residue through a mesh with cell sizes, mm:

Measuring, periodic, 3-4 times per shift, work log

for spray and primer - 3

for the top layer and single-layer coatings - 1.5

Solution mobility - 5

The same for each batch

Delamination - no more than 15%

The same, in laboratory conditions 3-4 times per shift

Water-holding capacity - at least 90%

Adhesion strength, MPa, not less than:

The same, at least 3 measurements per 50-70 sq.m of coating surface

for interior work - 0.1

for outdoor work - 0.4

Size of aggregates for decorative finishing of interiors and facades of buildings, mm:

The same, at least 5 measurements per batch per shift

on an adhesive layer of granite, marble, slate, ceramic, glass and plastic chips, as well as coarse sand - 2

cement-lime, lime-sand and cement compositions with sand:

quartz - 0.5

marble - 0.25

Terrasite mixtures

with fine aggregate:

with medium filler:

mica - 2.5

with coarse aggregate:

Glass must arrive at the site without cracks, cut to size, complete with seals, sealants and fastening devices.

According to the project in accordance with standards and specifications

Technical inspection

Putties:

Measuring, periodic, at least 5 measurements per 50 - 70 sq.m of coating surface, work log

drying time - no more than 24 hours

adhesion strength, MPa:

after 24 hours not less than 0.1

after 72 hours not less than 0.2

viability - at least 20 minutes

Technical inspection, at least three test putties per batch, work log

The putty coating after drying should be smooth, without bubbles, cracks and mechanical inclusions

Painting and wallpaper materials

According to the project in accordance with standards and specifications

The same, at least three times per batch, work log

BUILDING REGULATIONS

INSULATING AND FINISHING COATINGS

SNiP 3.04.01-87

STATE CONSTRUCTION COMMITTEE OF THE USSR

Moscow 1988

DEVELOPED BY TsNIIOMTP Gosstroy USSR (candidates of technical sciences) N.N. Zavrazhin- topic leader, V. A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the USSR State Construction Committee (candidate of technical sciences) I. P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences) D. K. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences, Prof. E. D. Belousov, Ph.D. tech. sciences G. S. Agadzhanov), SKTB Glavtonnelmetrostroy Ministry of Transport Construction of the USSR (candidates of technical sciences V. V. Krylova, V. G. Golubova), Office of the Soyuzmetrospetsstroy Ministry of Transport and Construction of the USSR ( A. P. Levina, P. F. Litvina), Research Institute of Reinforced Concrete Construction of the USSR State Construction Committee (Doctor of Technical Sciences, Prof. F. M. Ivanova).

INTRODUCED BY TsNIIOMTP Gosstroy USSR.

PREPARED FOR APPROVAL by the Department of Standardization and Technical Standards in Construction of the USSR State Construction Committee ( D. I. Prokofiev).

With the entry into force of SNiP 3.04.01-87 “Insulating and finishing coatings”, SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72 are no longer valid; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using a regulatory document, one should take into account the approved changes to building codes and regulations and state standards published in the journal “Bulletin of Construction Equipment”, “Collection of Amendments to Construction Codes and Rules” of the USSR State Construction Committee and the information index “USSR State Standards” of the USSR State Standard.

1. GENERAL PROVISIONS

1.1. These building codes and regulations apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to the special operating conditions of buildings and structures.

1.2. Insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - according to the standard). Replacement of materials, products and compositions provided for by the project is allowed only by agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can begin only after the execution of an act (permit) signed by the customer, representatives of the installation organization and the organization performing thermal insulation work.

1.4. The installation of each insulation element (roof), floor, protective and finishing coatings should be carried out after checking the correct execution of the corresponding underlying element and drawing up an inspection report for hidden work.

1.5. With appropriate justification, in agreement with the customer and the design organization, it is allowed to prescribe methods for performing work and organizational and technological solutions, as well as establish methods, volumes and types of registration of quality control of work that differ from those provided for in these rules.

2. INSULATING COATINGS AND ROOFINGS

GENERAL REQUIREMENTS

2.1. Insulation and roofing work can be carried out from 60 to minus 30 °C in the environment (work using hot mastics - at an ambient temperature of at least minus 20 °C, using water-based compounds without antifreeze additives at least 5 °C).

2.2. In the foundations for roofing and insulation, in accordance with the project, the following work must be performed:

seal the seams between prefabricated slabs;

arrange temperature-shrinkable seams;

install embedded elements;

plaster sections of vertical surfaces of stone structures to the height of the junction of the rolled or emulsion-mastic roofing carpet and insulation.

2.3. Insulating compounds and materials must be applied in continuous and uniform layers or in one layer without gaps or sagging. Each layer must be laid on the hardened surface of the previous one, leveling the applied compounds, with the exception of paint ones. When preparing and preparing insulating compositions, the requirements of Table. 1.

Table 1

Technical requirements

Limit deviations

Bitumen and tar (pitch) must be used cleaned of impurities and dehydrated. Heating should not exceed, °C:

Measuring, periodic, but not less than 4 times per shift, work log

bitumen - 180

tar (pitch) - 140

Fillers (aggregates) must be sifted through a sieve with cell sizes, mm:

for sand - 1.5

for dusty ones - 2

for fibrous - 4

Permissible moisture content of fillers (aggregates):

for sand

for compositions with sealing additives

for other compounds

Temperature of emulsions and their components, °C:

The same, at least 5-6 times per shift, work log

bitumen - 110

emulsifier solution - 90

latex (when introduced into the emulsion) - 70

Minus 10 °C

Uniformity of bitumen distribution in bitumen perlite and bitumen expanded clay - 90%

The compaction coefficient of bitumen perlite and bitumen expanded clay under pressure of 0.67-0.7 MPa is not less than 1.6

Temperature when applying mastics, °C:

hot bitumen - 160

hot tar - 130

cold (in winter) - 65

Installation of insulation dispersedly reinforced with glass fiber (fiberglass fibres):

Measuring, periodic at least 16 measurements per shift (every 0.5 hours of work), work log

fiber sizes - 20 mm

The ratio by weight of aluminous cement to Portland cement is 90: 10

Heavy concrete for constructing roofs without an insulating coating (roof) must contain:

Measuring, periodic, at least 4 times per shift, work log

plasticizing and air-entraining additives, fillers made of fractionated sand and coarse crushed stone;

Portland cement - hydrophobic, containing no more than 6% calcium aluminate;

crushed stone of igneous rocks or gravel with a temporary resistance of at least 100 MPa in a water-saturated state; granulometric composition of crushed stone, mm:

sand protective layer size modulus - 2.1 - 3.15

Gravel and other frost-resistant mineral materials should be sorted and washed

PREPARATION OF BASES AND UNDERLYING INSULATION ELEMENTS

2.4. Dust removal of substrates must be carried out before applying primers and insulating compounds, including adhesive adhesives and mastics.

2.5. Leveling screeds (from cement-sand, gypsum, gypsum-sand mortars and asphalt concrete mixtures) should be arranged with grips 2-3 m wide along guides with leveling and compacting the surface.

2.6. The surface priming before applying adhesive and insulating compounds must be continuous without gaps or breaks. Priming of screeds made from cement-sand mortars should be done no later than 4 hours after their installation, using primers based on slowly evaporating solvents (with the exception of screeds with a surface slope of more than 5%, when priming should be done after they have hardened). When preparing the base surface, it is necessary to comply with the requirements of Table. 2.

The primer must have strong adhesion to the base, and there should be no traces of binder left on the tampon attached to it.

table 2

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible deviations of the base surface for roll and non-roll emulsion and mastic insulation and roofing:

Measuring, technical inspection, at least 5 measurements for every 70-100 m2 of surface or on a smaller area in places determined by visual inspection

along a slope and on a horizontal surface

across a slope and on a vertical surface

from piece materials:

along and across the slope

Deviations of the element plane from a given slope (over the entire area)

Thickness of the structural element (from design)

Number of irregularities (smooth outline with a length of no more than 150 mm) on a surface area of ​​4 m2

No more than 2

Primer thickness, mm:

for roofs made of fused materials - 0.7

when priming a hardened screed - 0.3

when priming screeds within 4 hours after applying the solution - 0.6

2.7. The humidity of the base before applying the primer should not exceed the values ​​​​indicated in the table. 3. Only water-based primers or insulating compounds may be applied to wet substrates if the moisture appearing on the surface of the substrate does not violate the integrity of the coating film.

2.8. Metal surfaces of pipelines, equipment and fasteners to be insulated must be cleaned of rust, and those subject to anti-corrosion protection must be treated in accordance with the design.

2.9. Insulation of installed equipment and pipelines should be carried out after they are permanently secured in the designed position. Thermal insulation of equipment and pipelines in places that are difficult to reach for insulation must be carried out completely before installation, including the installation of cover shells.

Insulation of pipelines located in non-passing channels and trays must be performed before they are installed in the channels.

2.10. Equipment and pipelines filled with substances must be cleared of them before insulation work begins.

2.11. When working in sub-zero temperatures, rolled insulating materials must be heated to a temperature of at least 15 °C within 20 hours, rewound and delivered to the installation site in an insulated container.

2.12. When insulating roofs from large-sized complex panels with a factory-applied roofing carpet, sealing the joints of the roof panels and gluing them must be done after checking the insulation of the mounted panels.

INSULATION AND ROOFING FROM ROLL MATERIALS

2.13. Roofing and waterproofing carpets made of rolled materials with a mastic layer pre-fused at the factory must be glued onto a pre-primed base by melting or liquefying (plasticizing) the mastic layer of the material without the use of adhesive mastics. The adhesive strength must be at least 0.5 MPa.

Liquefaction of the mastic layer must be carried out at an air temperature of at least 5 ° C with the simultaneous laying of the rolled carpet or before its laying (depending on the ambient temperature).

Melting of the mastic layer should be carried out simultaneously with the laying out of the panels (temperature of the molten mastic is 140-160 ° C). Each laid roof layer must be rolled with a roller before installing the next one.

2.14. Before sticking, roll materials must be marked at the place of installation; The layout of the panels of rolled materials must ensure that their overlap values ​​are observed when gluing.

In accordance with the design, the mastic must be applied in a uniform continuous layer, without gaps or in stripes. When spot gluing panels to the base, mastic should be applied after rolling out the panels at the locations of the holes.

2.15. When installing roll insulation or roofing using adhesives, hot mastics should be applied to the primed base immediately before gluing the panels. Cold mastics (glues) should be applied to the base or panel in advance. Between applying the adhesive compositions and gluing the panels, it is necessary to observe technological breaks to ensure strong adhesion of the adhesive compositions to the base.

Each layer should be laid after the mastics have hardened and achieved strong adhesion to the base of the previous layer.

2.16. When installing roofs, sheets of rolled materials should be glued:

in the direction from low areas to high ones with the panels located along the length perpendicular to the water flow with roof slopes of up to 15%;

in the direction of drainage - with roof slopes of more than 15%.

Cross-sticking of insulation panels and roofing is not allowed. The type of roll carpet sticker (solid, striped or dotted) must correspond to the project.

2.17. When gluing, the insulation and roof panels must be overlapped by 100 mm (70 mm across the width of the panels of the lower layers of the roof of roofs with a slope of more than 1.5%).

2.18. When installing insulation or roofing, fiberglass fabric must be spread, laid without creating waves, immediately after applying hot mastic and covered with mastic with a thickness of at least 2 mm.

Subsequent layers should be laid similarly after the mastic of the lower layer has cooled.

2.19. Temperature-shrinkage seams in screeds and joints between coating slabs must be covered with strips of rolled material up to 150 mm wide and glued to one side of the seam (joint).

2.20. In places adjacent to protruding roof surfaces (parapets, pipelines, etc.), the roofing carpet must be raised to the top of the screed side, glued with mastic and putty on the upper horizontal seams. Gluing additional layers of roofing should be done after installing the top layer of the roof, immediately after applying the adhesive mastic in a continuous layer.

2.21. When gluing panels of roofing carpet along the roof slope, the upper part of the panel of the lower layer must overlap the opposite slope by at least 1000 mm. The mastic should be applied directly under the rolled roll in three strips 80-100 mm wide. Subsequent layers must be glued on a continuous layer of mastic.

When gluing panels across the roof slope, the upper part of the panel of each layer laid on the ridge should overlap the opposite roof slope by 250 mm and be glued to a continuous layer of mastic.

2.22. When installing a protective gravel coating on the roofing carpet, it is necessary to apply hot mastic in a continuous layer 2 - 3 mm thick and 2 m wide, immediately scattering over it a continuous layer of gravel, cleared of dust, 5-10 mm thick. The number of layers and total thickness of the protective coating must correspond to the design.

2.23. When installing roll insulation and roofing, it is necessary to comply with the requirements of Table. 3.

Table 3

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The permissible moisture content of the substrates when applying all compositions, except for water-based compositions, should not exceed:

Measuring, technical inspection, at least 5 measurements evenly for every 50-70 m2 of base, registration

concrete

cement-sand, gypsum and gypsum-sand

any bases when applying water-based compounds

Before surface moisture appears

Temperature when applying hot mastics, °C:

Measuring, periodic, at least 4 times per shift, work log

bitumen - 160

tar - 130

Thickness of the mastic layer when gluing a rolled carpet, mm:

hot bitumen - 2.0

intermediate layers - 1.5

cold bitumen - 0.8

Thickness of one insulation layer, mm:

Measuring, technical inspection, at least 5 measurements for every 70-100 m2 in places determined by visual inspection, work log

cold asphalt mastics - 7

cement mortars - 10

emulsions - 3

polymer compositions (such as “Krovlelit” and “Venta”) - 1

INSULATION AND ROOFING DEVICE FROM POLYMER AND EMULSION-BITUMEN COMPOSITIONS

2.24. When installing insulation and roofs made from emulsion-mastic compositions, each layer of the insulating carpet must be applied continuously, without breaks, of uniform thickness after the primer or bottom layer has hardened.

2.25. When installing insulation and roofing from polymer compositions such as “Krovlelit” and “Venta”, they must be applied with high-pressure units that ensure density, uniform thickness of the coating and adhesion strength of the coating to the base of at least 0.5 MPa. When using cold asphalt emulsion mastics, the supply and application of the compositions should be carried out by units with screw pumps (mechanical action), ensuring the adhesion strength of the coating to the base of at least 0.4 MPa.

2.26. When installing insulation and roofing from emulsion-mastic compositions reinforced with fiberglass fibers, their application should be carried out with units that ensure the production of fibers of the same length, uniform distribution in the composition and density of the insulating coating.

2.27. When installing insulation and roofing made of polymer and emulsion-mastic compositions, the requirements of Table 1 must be met. 3. Roof junctions should be arranged similarly to the installation of roll roofs.

INSULATION DEVICE FROM CEMENT SOLUTIONS, HOT ASPHALT MIXTURES, BITUMEN-PERLITE AND BITUMEN-CERAMZITE

2.28. Bitumen perlite, bitumen expanded clay, cement mortars, hot asphalt mixtures with a surface slope of up to 25% must be laid along lighthouse slats in strips 2-6 m wide in layers of uniform thickness (no more than 75 mm) with compaction and smoothing of the layer surface.

Each layer must be laid after the previous one has hardened.

2.29. When installing cement waterproofing from mortars using waterproof expanding cements (WRC), waterproof non-shrinking cements (WBC) or Portland cement with compacting additives, the compositions should be applied to the base surface wetted with water.

Each subsequent layer must be applied no later than 30 minutes (when using VRC and VBC compositions) or no more than 24 hours (when using Portland cement compositions with sealing additives) after hardening of the previous layer.

Cement waterproofing must be protected from mechanical influences for two days after application (1 hour when using VBC and VRC).

2.30 Moistening of cement waterproofing during hardening should be carried out with a sprayed stream of water without pressure when using the following compositions:

VRC and VBC - 1 hour after application and every 3 hours during the day;

on Portland cement with sealing additives - 8-12 hours after application, and then 2-3 times a day for 14 days.

2.31. When installing insulation from bitumen perlite, bitumen expanded clay, waterproofing from cement mortars and hot asphalt mixtures, mastics and bitumens, it is necessary to comply with the requirements of Table. 4.

Table 4

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible surface deviations (when checked with a two-meter rod):

Measuring, at least 5 measurements for every 50 - 100 m2 of surface or on a smaller area in places determined by visual inspection

horizontally

vertically

5 ... + 10 mm

element plane from a given slope - 0.2%

No more than 150 mm

coating element thickness - -5 ... + 10%

No more than 3.0 mm

Mobility of compositions (mixtures) without plasticizers, cm:

Measuring, at least 3 measurements for every 70-100 m2 of coating surface

when applied manually - 10

when applied by installations with piston or screw pumps - 5

when using plasticizers - 10

The temperature of hot asphalt mixtures, bitumen perlite and bitumen expanded clay during application is at least 120 ° C

Measuring, periodic, at least 8 times per shift, work log

PRODUCTION OF THERMAL INSULATION WORKS USING SOFT, HARD AND SEMI-HARD FIBER PRODUCTS AND CONSTRUCTION OF THERMAL INSULATION COVERS FROM HARD MATERIALS

2.32. When constructing cover shells from flat or corrugated asbestos-cement sheets, their installation and fastening must comply with the design.

When constructing thermal insulation cover shells made of rigid and flexible (non-metallic) materials, it is necessary to ensure a tight fit of the shells to the thermal insulation with reliable fastening using fasteners and thorough sealing of the joints of flexible shells with their gluing in accordance with the design.

On pipelines with a diameter of up to 200 mm, fiberglass should be laid spirally, on pipelines with a diameter of more than 200 mm - in separate panels in accordance with the requirements of the project.

2.33. Installation of thermal insulation structures and cover shells must begin from unloading devices, flange connections, curved sections (bends) and fittings (tees, crosses) and be carried out in the direction opposite to the slope, and on vertical surfaces - from bottom to top.

2.34. When installing thermal insulation from rigid products laid dry, a gap of no more than 2 mm must be provided between the products and the insulated surface.

When gluing hard products, the temperature of the mastics must meet the requirements of Table. 3. Fastening of products to the base must correspond to the project.

2.35. When installing thermal insulation of pipelines using soft and semi-rigid fibrous products, it is necessary to ensure:

compaction of thermal insulation materials according to the project with a compaction coefficient for soft fibrous products of no more than 1.5, for semi-rigid ones - 1.2;

tight fit of products to the insulated surface and to each other; when insulating in several layers - overlap longitudinal and transverse seams;

dense spiral laying of insulation with cords and bundles with minimal deviation relative to the plane perpendicular to the axis of the pipeline, and winding in multilayer structures of each subsequent layer in the direction opposite to the turns of the previous layer;

installation of fasteners on horizontal pipelines and devices to prevent sagging of thermal insulation.

THERMAL INSULATION DEVICE FROM PLATES AND BULK MATERIALS

2.36. When installing thermal insulation from slabs, insulation materials must be laid on the base tightly to each other and have the same thickness in each layer.

When installing thermal insulation in several layers, the seams of the slabs must be spaced apart.

2.37. Thermal insulation bulk materials must be sorted into fractions before installation. Thermal insulation must be installed along lighthouse slats in strips 3-4 m wide with loose insulation of smaller fractions laid in the lower layer.

Layers should be laid with a thickness of no more than 60 mm and compacted after laying.

2.38. When installing thermal insulation from slabs and bulk materials, the requirements of Table. 5 and 6.

Table 5

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The permissible moisture content of the bases should not exceed:

Measuring, at least 5 measurements for every 50-70 m2 of coverage, work log

from prefabricated

from monolithic

Thermal insulation made from piece materials

The thickness of the interlayer layer should not exceed, mm:

from adhesives and cold mastics - 0.8

from hot mastics - 1.5

width of joints between slabs, blocks, products, mm:

when sticking - no more than 5 (for hard products - 3)

when laying dry - no more than 2

Monolithic and slab thermal insulation:

insulation coating thickness (from design)

5 ... + 10% but not more than 20 mm

Deviations of the insulation plane:

Measuring, for every 50-100 m2 of coating surface

from a given slope

horizontally

vertically

The size of the ledges between tiles and roofing sheets should not exceed 5 mm

The amount of overlap of slabs and sheets must correspond to the design - 5%

Table 6

CONSTRUCTION OF ROOFS FROM PIECES MATERIALS

2.39. When installing wooden foundations (lathing) under roofs made of piece materials, the following requirements must be observed:

the joints of the sheathing should be spaced apart;

the distances between the sheathing elements must correspond to the design ones;

in places where eaves overhangs, valleys and valleys are covered, as well as under roofs made of small-piece elements, the foundations must be made of boards (solid).

2.40. Piece roofing materials should be laid on the sheathing in rows from the eaves to the ridge according to preliminary markings. Each overlying row must overlap the underlying one.

2.41. Corrugated asbestos-cement sheets of ordinary profile and medium-wavy must be laid offset by one wave in relation to the sheets of the previous row or without offset. Sheets of reinforced and unified profiles must be laid in relation to the sheets of the previous row without displacement.

When laying sheets without displacement on a wave at the junction of four sheets, the corners of the two middle sheets should be trimmed with a gap between the joining corners of the VO sheets of 3-4 mm and the SV, UV and VU sheets - 8-10 mm.

2.42. Asbestos-cement sheets VO and SV should be fastened to the sheathing with slate nails with a galvanized head, sheets UV and VU - with screws with special grips, flat sheets - with two nails and an anti-wind button, outer sheets and ridge parts - in addition with two anti-wind brackets.

2.43. When installing roofs made of piece materials, the requirements of Table. 4.

INSULATION AND ROOF DETAILS FROM METAL SHEETS

2.44. Metal waterproofing must be installed by welding sheets in accordance with the project. After welding, the filling of the cavities behind the insulation should be injected with a composition under a pressure of 0.2-0.3 MPa.

2.45. When installing metal roofs, parts and junctions from metal sheets of any type of roof, the connection of paintings located along the water drainage must be carried out using lying seams, except for ribs, slopes and ridges, where the paintings must be connected with standing seams. For roof slopes of less than 30°, the rebated seam should be made double and coated with red lead putty. The amount of folding of the paintings for the installation of recumbent folds should be taken as 15 mm; standing seams - 20 mm for one and 35 mm for another adjacent picture. The paintings must be secured to the base with clamps passed between the folds of the sheets and T-shaped crutches.

REQUIREMENTS FOR READY INSULATION (ROOF) COATINGS AND STRUCTURAL ELEMENTS

2.46. The requirements for finished insulating (roofing) coverings and structures are given in Table. 7.

Table 7

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Complete drainage of water over the entire surface of the roofs should be carried out through external and internal drains without stagnation of water

The adhesion strength to the base and to each other of roofing and waterproofing carpet made from rolled materials over a continuous mastic adhesive layer of emulsion compositions with the base is not less than 0.5 MPa

Measuring, 5 measurements per 120-150 m 2 of the coating surface (the nature of the sound should not change when tapping); when the glued materials rupture, there should be no peeling of the mastic (the rupture should occur inside the rolled panel), acceptance certificate

The heat resistance and compositions of mastics for gluing rolled and slab materials, as well as the strength and compositions of adhesive layer solutions must correspond to the design. Deviations from the project - 5%

Technical inspection, acceptance certificate

The location of panels and metal paintings (depending on the slope of the coating), their connection and protection in a regular coating, in places of abutments and interfaces in different planes must correspond to the project

Bubbles, swelling, air pockets, tears, dents, punctures, spongy structure, drips and sagging on the surface of roof coverings and insulation are not allowed

Increased humidity of bases, intermediate elements, coating and the entire structure compared to the standard

No more than 0.5%

Measuring, 5 measurements on an area of ​​50-70 m2 of the coating surface or on individual areas of a smaller area in places identified by visual inspection, acceptance certificate

When accepting finished insulation and roofing, you must check:

Deviations from the project are not allowed

Technical inspection, acceptance certificate

correspondence of the number of reinforcing (additional) layers in mates (adjacents) to the project;

for waterproofing:

the quality of filling joints and holes in structures made of prefabricated elements with sealing materials;

quality of caulking;

correct waterproofing of bolt holes, as well as holes for injection of solutions for finishing structures;

absence of leaks and discontinuities of seam lines in metal waterproofing;

for roofs made of rolled materials, emulsion, mastic compositions:

the bowls of the water inlet funnel of internal drains should not protrude above the surface of the base;

the corners of adjoining structures (screeds and concrete) must be smooth and even, without sharp corners;

for roofs made of piece materials and roof parts made of metal sheets:

absence of visible gaps in the coating when inspecting the roof from the attic;

absence of chips and cracks (in asbestos-cement and sealed flat and corrugated sheets);

strong connection of drainpipe links to each other;

the presence of smearing of double recumbent seams in the joints of metal paintings on a coating with a slope of less than 30°;

for thermal insulation:

continuity of layers, quality of lining of passage points for pipeline fastenings, equipment, structural parts, etc. through thermal insulation;

absence of mechanical damage, sagging layers and loose fit to the base

3. FINISHING WORKS AND PROTECTION OF BUILDING STRUCTURES AND TECHNOLOGICAL EQUIPMENT FROM CORROSION (ANTI-CORROSION WORK)

GENERAL PROVISIONS

3.1. Finishing work, with the exception of finishing facades, must be carried out at a positive ambient temperature and the surfaces being finished are not lower than 10 ° C and air humidity is not more than 60%. This temperature in the room must be maintained around the clock, no less than 2 days before the start and 12 days after the completion of work, and for wallpaper work - before the facility is put into operation.

3.2. Work on applying protective coatings should be carried out at a temperature of the ambient air and protected surfaces not lower than, °C:

10 - for paint and varnish protective coatings made from compositions prepared on the basis of natural resins; mastic and putty coatings made of silicate compounds; adhesive protective coatings using bitumen roll materials, polyisobutylene plates, Butylkor-S plates, duplicated polyethylene; rubber coatings; facing and lining coatings using acid-resistant silicate putties and mastics such as “Bituminol”; for acid-resistant concrete and silicate polymer concrete;

15 - for paint and varnish reinforced and non-reinforced continuous coatings from compositions prepared on the basis of synthetic resins; mastic coatings and sealants made from compounds based on synthetic rubbers and nairite; coatings made of sheet polymer materials; facing and lining coatings using putties such as “Arzamit”, “Furankor”, as well as polyester, epoxy resins and resins with epoxy additives; for coatings made of polymer concrete and polymer cement coatings;

25 - for coatings made from Polan.

3.3. Finishing work must be carried out in accordance with the work project (WPP) for the construction of buildings and structures. Before finishing work begins, the following work must be completed:

the premises being finished are protected from precipitation;

waterproofing, heat and sound insulation and leveling floor ties were installed;

the seams between the blocks and panels are sealed;

the joints of window, door and balcony blocks are sealed and insulated;

glazed light openings;

embedded products were installed, heat and water supply and heating systems were tested.

Plastering and cladding (according to the project) of surfaces in places where embedded products of sanitary systems are installed must be performed before the start of their installation.

3.4. Before finishing the facades, the following work must additionally be completed:

external waterproofing and roofing with details and connections; installation of all floor structures on balconies;

installation and fastening of all metal paintings edging architectural details on the facade of the building;

installation of all fastening devices for drainpipes (according to the project).

3.5. Anti-corrosion work should be carried out in accordance with the requirements of SNiP 3.04.03-85 “Protection of building structures and structures from corrosion”.

3.6. When preparing and preparing finishing and anti-corrosion compounds, it is necessary to comply with the requirements of Table. 8.

Table 8

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Plastering solutions must pass without residue through a mesh with cell sizes, mm:

Measuring, periodic, 3-4 times per shift, work log

for spray and primer - 3

for the top layer and single-layer coatings - 1.5

Solution mobility - 5

The same for each batch

Delamination - no more than 15%

The same, in laboratory conditions 3-4 times per shift

Water-holding capacity - at least 90%

Adhesion strength, MPa, not less than:

The same, at least 3 measurements per 50-70 m2 of coating surface

for interior work - 0.1

for outdoor work - 0.4

Size of aggregates for decorative finishing of interiors and facades of buildings, mm:

The same, at least 5 measurements per batch per shift

on an adhesive layer of granite, marble, slate, ceramic, glass and plastic chips, as well as coarse sand - 2

cement-lime, lime-sand and cement compositions with sand:

quartz - 0.5

marble - 0.25

Terrasite mixtures

with fine aggregate:

with medium filler:

mica - 2.5

with coarse aggregate:

Glass must arrive at the site without cracks, cut to size, complete with seals, sealants and fastening devices.

According to the project in accordance with standards and specifications

Technical inspection

Putties:

Measuring, periodic, at least 5 measurements per 50 - 70 m2 of coating surface, work log

drying time - no more than 24 hours

adhesion strength, MPa:

after 24 hours not less than 0.1

after 72 hours not less than 0.2

viability - at least 20 minutes

Technical inspection, at least three test putties per batch, work log

The putty coating after drying should be smooth, without bubbles, cracks and mechanical inclusions

Painting and wallpaper materials

According to the project in accordance with standards and specifications

The same, at least three times per batch, work log

SURFACE PREPARATION

3.7. Finishing and protective coatings on substrates that have rust, efflorescence, grease and bitumen stains are not permitted. Wallpaper production is also not allowed on surfaces that have not been whitewashed.

3.8. Dust removal of surfaces should be carried out before applying each layer of priming, gluing, plastering, painting and protective compounds, coatings and glass putties.

3.9. The strength of the bases must be no less than the strength of the finishing coating and correspond to the design.

3.10. Protruding architectural details, places where they meet wooden stone, brick and concrete structures must be plastered over a metal mesh or woven wire attached to the surface of the base; wooden surfaces - on shingle panels.

3.11. The internal surfaces of stone and brick walls constructed using the freezing method should be plastered after thawing of the masonry from the inside to at least half the thickness of the wall.

3.12. When painting and wallpapering, the quality of the prepared substrates must meet the following requirements:

surfaces when painted with oil, adhesive, water-based compositions and wallpapering should be smooth, without roughness;

surface cracks are opened, primed, filled with putty to a depth of at least 2 mm and sanded;

shells and irregularities are primed, puttied and smoothed;

peelings, mortar drips, traces of processing by trowelling machines have been removed;

the seams between sheets of dry gypsum plaster and the areas adjacent to them are primed, puttied, sanded flush with the surface or rusticated (in accordance with the project), and when wallpapering, they are additionally covered with strips of paper, gauze, etc.;

When the surfaces were covered with wallpaper, the ceilings were painted and other painting work was completed.

Substrates prepared for painting, pasting with synthetic wallpaper on paper and fabric basis, as well as with a factory-applied adhesive composition must meet the requirements of Table. 9. The surfaces of all fastening devices located under cardboard, paper or directly under wallpaper must be pre-coated with an anti-corrosion compound.

Table 9

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Plastered surfaces

Measuring, at least 5 measurements with a control two-meter rod on 50-70 m 2 of the surface or on a separate area of ​​​​a smaller area in places identified by a continuous visual inspection (for molded products - at least 5 at 35-40 m and three per element), work log

deviations from the vertical (mm per 1 m), mm:

with simple plaster - 3

No more than 15 mm per room height

the same, improved - 2

The same, no more than 10 mm

the same, high quality - 1

The same, no more than 5 mm

uneven surfaces of a smooth outline (per 4 m2):

with simple plaster - no more than 3, depth (height) up to 5 mm

the same, improved - no more than 2, depth (height) up to 3 mm

the same, high quality - no more than 2, depth (height) up to 2 mm

Horizontal deviations (mm per 1 m) should not exceed, mm:

with simple plaster - 3

the same, improved - 2

the same, high quality - 1

Deviations of window and door slopes, pilasters, pillars, husks, etc. from the vertical (mm per 1 m) should not exceed, mm:

The same, except measurements (3 by 1 mm)

with simple plaster - 4

Up to 10 mm for the entire element

the same, improved - 2

The same, up to 5 mm

the same, high quality - 1

The same, up to 3 mm

Deviations of the radius of curved surfaces, checked by a pattern, from the design value (for the entire element) should not exceed, mm:

Measuring, at least 5 measurements with a control two-meter rod on 50 - 70 m 2 of the surface or on a separate area of ​​​​a smaller area in places identified by a continuous visual inspection (for molded products - at least 5 at 35-40 m and three per element) except for measurements ( 3 by 1 mm), work log

with simple plaster - 10

the same, improved - 7

the same high quality - 5

Deviations of the slope width from the design should not exceed, mm:

with simple plaster - 5

the same, improved - 3

the same, high quality - 2

Deviations of the rods from a straight line within the limits between the angles of intersection of the rods and the bracing should not exceed, mm:

with simple plaster - 6

the same, improved - 3

the same, high quality - 2

The surfaces of prefabricated slabs and panels must meet the requirements of the standards and specifications for the relevant products

Permissible humidity:

Measuring, at least 3 measurements per 10 m 2 surface

brick and stone surfaces when plastered, concrete, plastered or puttied surfaces when wallpapering and when painting with painting compounds, except cement and lime

No more than 8%

the same when painting with cement and lime compounds

Until droplet moisture appears on the surface

wooden surfaces for painting

No more than 12%

When installing paint coatings, the surface of the base must be smooth, without roughness; local irregularities with a height (depth) of up to 1 mm - no more than 2 on an area of ​​4 m 2 of the coating surface

3.13. When covering surfaces, the quality of the prepared bases must meet the following requirements:

walls must have a load of at least 65% of the design load for internal and 80% for external cladding of their surface, with the exception of walls whose cladding is carried out simultaneously with masonry;

concrete surfaces and surfaces of brick and stone walls laid with completely filled joints must have a notch;

the surfaces of walls laid out in hollow areas must be prepared without notching them and filling the joints with mortar;

Before covering, any surfaces must be cleaned, rinsed and moistened to a matte shine before applying an adhesive layer of solution and other aqueous compounds;

Before tiling in the premises, the ceilings and the plane of the walls above the surface to be tiled should be painted. Before covering the walls with sheets and panels with a front finish, also arrange hidden wiring.

3.14. When preparing facing and other types of surfaces during finishing work, the requirements of Table 1 must be met. 9.

PRODUCTION OF PLASTERING AND STUCKING WORKS

3.15. When plastering brick walls at an ambient temperature of 23 °C and above, the surface must be moistened before applying the solution.

3.16. Improved and high-quality plaster should be performed along beacons, the thickness of which should be equal to the thickness of the plaster coating without a covering layer.

3.17. When installing single-layer coatings, their surface should be leveled immediately after applying the solution; in the case of using trowels, after it has set.

3.18. When installing a multi-layer plaster coating, each layer must be applied after the previous one has set (the covering layer - after the mortar has set). Leveling the soil should be done before the mortar begins to set.

3.19. Sheets of gypsum plaster must be glued to the surface of brick walls with compositions corresponding to the design, placed in the form of marks, measuring 80´80 mm over an area of ​​at least 10% along the ceiling, floor, corners of the vertical plane every 120-150 mm, in the spaces between them at a distance no more than 400 mm, along vertical edges - in a continuous strip. Sheets should be fastened to wooden bases with nails with wide heads.

3.20. Installation of gypsum moldings should be done after the base of plaster mortars has set and dried. Architectural details on the facade must be secured to the reinforcement embedded in the wall structure, which is previously protected from corrosion.

3.21. When performing plastering work, the requirements of Table. 10.

Table 10

Technical requirements

Control (method, volume, type of registration)

Permissible thickness of single-layer plaster, mm:

when using all types of solutions, except gypsum - up to 20, from gypsum solutions - up to 15

Permissible thickness of each layer when installing multilayer plasters without polymer additives, mm:

Measuring, at least 5 measurements per 70-100 m 2 of the coating surface or in one room of a smaller area in places identified by a continuous visual inspection, work log

spray on stone, brick, concrete surfaces - up to 5

spray on wooden surfaces (including the thickness of the shingles) - up to 9

soil from cement mortars - up to 5

soil from lime, lime-gypsum solutions - up to 7

covering layer of plaster coating - up to 2

covering layer of decorative finishing - up to 7

PRODUCTION OF PAINTING WORKS

3.22. Painting work on facades should be carried out by protecting the applied compositions (until they are completely dry) from direct exposure to sunlight.

3.23. When performing painting work, continuous filling of the surface should be performed only with high-quality painting, and with improved paint - on metal and wood.

3.24. Putty made from low-shrinkage compounds with polymer additives must be leveled immediately after application with grinding of individual areas; When applying other types of putty compounds, the surface of the putty should be sanded after it has dried.

3.25. Surfaces must be primed before painting with painting compounds, except organosilicon. The primer must be applied in a continuous, uniform layer, without gaps or breaks. The dried primer should have strong adhesion to the base, not peel off when stretched, and no traces of binder should remain on the tampon attached to it. Painting should be done after the primer has dried.

3.26. Painting compounds must also be applied in a continuous layer. The application of each paint composition should begin after the previous one has completely dried. Flatting or trimming of the paint composition should be done using freshly applied paint composition.

33.7. When painting plank floors, each layer, with the exception of the last, must be sanded until the gloss is removed.

3.28. When performing painting work, the requirements of Table. eleven.

Table 11

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Permissible thickness of paint coating layers:

Measuring, at least 5 measurements per 50-70 m2 of coating surface or in one smaller room, after a complete visual inspection, work log

putty - 0.5 mm

paint coating - at least 25 microns

The surface of each layer of paint coating with improved and high-quality interior painting with anhydrous compounds must be smooth, without paint drips, not have a jagged structure, etc.

The same, on 70-100 m 2 of the coating surface (when illuminated by an electric lamp with a reflector having a narrow slit, a beam of light directed parallel to the painted surface should not form shadow spots)

PRODUCTION OF DECORATIVE FINISHING WORKS

3.29. When decorative finishing with compositions with fillers, the surface of the base must be unsmoothed; Puttying and grinding of rough surfaces is not allowed.

3.30. When finishing surfaces with decorative pastes and terrazite compositions, each layer of multilayer decorative coatings must be performed after the previous one has hardened, without grinding the front surface.

3.31. When installing finishing coatings from decorative pastes on plaster instead of a covering layer, the work should be carried out in compliance with the rules for installing a covering layer of plaster coatings.

3.32. Decorative finishing with terrazite compositions must be carried out in a single layer in compliance with the requirements for the installation of single-layer plaster coatings.

3.33. When finishing surfaces with decorative chips, it must be applied over a wet adhesive layer. The applied crumbs must have a strong (at least 0.8 MPa) adhesion to the base and form a continuous, gap-free coating with the crumbs tightly adjacent to each other.

Before applying the water-repellent composition, the surface must be cleaned with compressed air.

3.34. When installing decorative finishing coatings, the requirements of Table. 12.

Table 12

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The amount of decorative chips embedded into the adhesive layer should be 2/3 of its size

Measuring, at least 5 measurements per 50-70 m 2 surface in places identified by continuous visual inspection, work log

The adhesion of decorative chips to the base must be at least 0.3 MPa

The same, at least 5 measurements per 70-100 m 2, work log

Permissible thickness of decorative coating, mm:

The same, at least 5 measurements for every 30-50 m2 of coating surface

using crumbs on an adhesive layer - up to 7

using pastes (for plaster) - up to 5

using terrasite compounds - up to 12

PRODUCTION OF WALLPAPER WORKS

3.35. When priming the surface under wallpaper, the adhesive composition must be applied in a continuous, uniform layer, without gaps or drips, and left until thickening begins. An additional layer of adhesive layer should be applied along the perimeter of window and door openings, along the contour and in the corners of the surface to be finished in a strip 75-80 mm wide at the moment the base layer begins to thicken.

3.36. When gluing bases with paper in separate strips or sheets, the distance between them should be 10-12 mm.

3.37. Gluing panels of paper wallpaper should be done after they have swollen and been impregnated with adhesive.

3.38. Wallpaper with a surface density of up to 100 g/m2 must be glued overlapping, 100-120 g/m2 or more - back to back.

3.39. When joining panels with an overlap, pasting surfaces with wallpaper must be done in the direction from the light openings without making joints of vertical rows of panels at the intersections of planes.

3.40. When gluing surfaces with synthetic wallpaper on a paper or fabric basis, the corners of the walls must be covered with a whole panel. Glue stains on their surface must be removed immediately.

When gluing, the vertical edges of adjacent textvinite panels and fabric-based films should overlap in width the previous panel with an overlap of 3-4 mm. Trimming overlapping edges should be done after the adhesive layer has completely dried, and after removing the edge, additionally apply glue in the places where the edges of adjacent panels are glued.

3.41. When gluing pile wallpaper, the panels should be smoothed in one direction when gluing.

3.42. When covering surfaces with wallpaper, the formation of air bubbles, stains and other contaminants, as well as additional adhesion and peeling, is not allowed.

3.43. When wallpapering, the premises must be protected from drafts and direct exposure to sunlight until the wallpaper is completely dry and a constant humidity regime must be established. The air temperature when drying pasted wallpaper should not exceed 23 °C.

PRODUCTION OF GLASS WORKS

3.44. Glass work must be carried out at positive ambient temperatures. Glazing at negative air temperatures is allowed only if it is impossible to remove the bindings, using putty heated to at least 20 °C.

3.46. When glazing metal and reinforced concrete frames, metal glazing beads must be installed after laying rubber gaskets in the rebate.

3.46. Fastening glass in wooden frames should be done using glazing beads or pins and filling the binding folds with putty. The glass should overlap the binding folds by no more than 3/4 of the width. The putty should be applied in an even, continuous layer, without breaks, until the binding fold is completely sealed.

3.47. Joining glass, as well as installing glass with defects (cracks, chips of more than 10 mm, permanent stains, foreign inclusions) when glazing residential buildings and cultural and community facilities is not allowed.

3.48. Fastening of uviol, frosted, frosted-patterned, reinforced and colored glass, as well as tempered glass in window and door openings should be done in the same way as sheet glass, depending on the binding material.

3.49. Installation of glass blocks on mortar should be carried out with strictly constant horizontal and vertical joints of constant width in accordance with the project.

3.50. Installation of glass panels and assembly of their trims must be carried out in accordance with the project.

PRODUCTION OF FACING WORKS

3.51. Surface cladding must be carried out in accordance with the PPR in accordance with the project. The connection of the cladding field to the base should be carried out:

when using facing slabs and blocks with a size of more than 400 cm 2 and a thickness of more than 10 mm - by fastening to the base and filling the space between the cladding and the wall surface (sinuses) with mortar, or without filling the sinuses with mortar when the cladding is removed from the wall;

when using slabs and blocks measuring 400 cm 2 or less, with a thickness of no more than 10 mm, as well as when facing horizontal and inclined (no more than 45%) surfaces with slabs of any size - on mortar or mastic (in accordance with the project) without additional fastening to basis;

when facing with embedded slabs and facing bricks simultaneously with the laying of walls - on masonry mortar.

3.52. Cladding of walls, columns, pilasters of interiors should be done before installing the floor covering.

3.53. Cladding elements on an adhesive layer of mortar and mastic must be installed in horizontal rows from bottom to top from the corner of the cladding field.

3.54. The mastic and adhesive layer solution should be applied in a uniform, streak-free layer before installing the tiles. Small-sized tiles on mastics or mortars with retarders should be installed after applying the latter over the entire area to be tiled in one plane when the mastics and mortars with retarders thicken.

3.55. Finishing of the site and the entire surface of the interior and facade with cladding products of different colors, textures, textures and sizes should be done with the selection of the entire pattern of the cladding field in accordance with the project.

3.56. When using natural and artificial stone of polished and polished texture, cladding elements must be mated dry, adjusting the edges of adjacent slabs selected according to the design with fastening according to the design. The seams of the slabs must be filled with mastic after the sinuses have been filled with mortar and it has hardened.

3.57. Slabs with a polished, dotted, bumpy and grooved structure, as well as with a “rock” type relief, must be installed on mortar; vertical joints should be filled with mortar to a depth of 15 - 20 mm or sealant after the adhesive layer solution has hardened.

3.58. The seams of the cladding must be smooth and of the same width. When cladding walls built using the freezing method, filling the cladding joints from embedded ceramic slabs must be done after thawing and hardening of the masonry mortar with loads on the walls of at least 80% of the design load.

3.59. Filling the sinuses with a solution must be done after installing permanent or temporary fastening of the lining field. The solution should be poured in horizontal layers, leaving after pouring the last layer of solution a space of 5 cm to the top of the cladding.

The solution poured into the sinuses should be protected from moisture loss during process breaks exceeding 18 hours. Before continuing work, the unfilled part of the sinus must be cleared of dust with compressed air.

3.60. After cladding, the surfaces of slabs and products must be cleaned of mortar and mastic deposits immediately, while: the surfaces of glazed, polished and polished slabs and products are washed with hot water, and polished, dotted, bumpy, grooved and “rock” type surfaces are treated with 10% - with a solution of hydrochloric acid and steam using a sandblaster.

3.61. Surfaces from the cutting of soft rock slabs (limestone, tuff, etc.), as well as the edges of slabs with polished, ground, grooved and dotted surfaces protruding by more than 1.5 mm must be accordingly ground, sub-polished or hewn until clear contour of the edges of the slabs.

3.62. When performing facing work, the requirements of Table. 13.

Table 13

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Thickness of the adhesive layer, mm:

from solution - 7

from mastic - 1

Lined surface

The same, at least 5 measurements per 50-70 m 2 surface

deviations from the vertical (mm per 1 m length), mm:

mirrored, polished - no more than 2

No more than 4 per floor

polished, dotted, bumpy, grooved - no more than 3

No more than 8 per floor

ceramic, glass-ceramic and other cladding products

external - 2

No more than 5 per floor

internal - 1.5

No more than 4 per floor

deviations in the location of seams from the vertical and horizontal (mm per 1 m length) in the cladding, mm:

mirror, polished - up to 1.5

polished, dotted, bumpy, grooved - up to 3

“rock” type textures - up to 3

ceramic, glass-ceramic, and other cladding products:

external - up to 2

internal - up to 1.5

Permissible profile discrepancies at the joints of architectural details and seams, mm:

Measuring, at least 5 measurements on 70-100 m2 of surface or on a separate area of ​​​​a smaller area in places identified by a continuous visual inspection, work log

mirror, polished - up to 0.5

polished, dotted, bumpy, grooved - up to 1

“rock” type textures - up to 2

outdoor - up to 4

internal - up to 3

Unevenness of the plane (when controlled with a two-meter rod), mm:

mirrored, polished - up to 2

polished, dotted, bumpy, grooved - up to 4

ceramic, glass-ceramic and other cladding products:

external - up to 3

internal - up to 2

Deviations in the width of the cladding seam:

mirrored, polished

granite and artificial stone

marbles

polished, dotted, bumpy, grooved

"rock" type textures

ceramic, glass-ceramic and other products (internal and external cladding)

INSTALLATION OF SUSPENDED CEILINGS, PANELS AND PLATES WITH FRONT FINISH IN BUILDING INTERIORS

3.63. The installation of suspended ceilings must be done after installing and fastening all frame elements (in accordance with the project), checking the horizontalness of its plane and compliance with the marks.

3.64. Installation of slabs, wall panels and suspended ceiling elements should be done after marking the surface and start from the corner of the plane being tiled. Horizontal joints of sheets (panels) not provided for in the project are not allowed.

3.65. The plane of the surface, lined with panels and slabs, must be smooth, without sagging at the joints, rigid, without vibration of panels and sheets and peeling from the surface (when gluing).

3.66. When installing suspended ceilings, panels and slabs with front finishing in the interiors of buildings, the requirements of Table 1 must be met. 14.

Table 14

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Finished cladding:

Measuring, at least 5 measurements per 50-70 m 2 surface or individual areas of a smaller area, identified by continuous visual inspection, work log

maximum values ​​of ledges between slabs and panels, as well as slats (suspended ceilings) - 2 mm

Deviation of the plane of the entire finishing field diagonally, vertically and horizontally (from the design) by 1 m - 1.5 mm

7 over the entire surface

Deviation of the direction of the joint of wall cladding elements from the vertical (mm per 1 m) - 1 mm

REQUIREMENTS FOR READY FINISH COATINGS

3.67. The requirements for finished finishing coatings are given in table. 15.

Table 15

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Adhesion strength of coatings made of plaster compositions and sheets of dry gypsum plaster, MPa:

Measuring, at least 5 measurements per 50-70 m 2 of the coating surface or on the area of ​​individual areas identified by a continuous visual inspection, acceptance certificate

internal plastered surfaces - not less than 0.1

external plastered surfaces - 0.4

The unevenness of the plastered surface should have deviations and irregularities not exceeding those given in the table. 9 (for plaster coatings made of dry gypsum plaster, the indicators must correspond to high-quality plaster)

Plaster coatings made from sheets of dry gypsum plaster should not be unsteady; when lightly tapped with a wooden hammer, cracks should not appear in the joints; Sagging in joints is allowed no more than 1 mm

Moldings

Horizontal and vertical deviations per 1 m of part length - no more than 1 mm

The displacement of the axes of separately located large parts from the specified position should not exceed 10 mm

The sealed joints should not be noticeable, and parts of the closed relief should be in the same plane; the design (profile) of relief products must be clear; on the surface of the parts there should be no cavities, kinks, cracks, or sagging mortar

Acceptance of finishing coatings must be done after water-based paints have dried and a strong film has formed on surfaces painted with anhydrous compositions. After drying of aqueous compositions, surfaces must be uniform in color, without stripes, stains, smudges, splashes, or abrasion (chalking) of surfaces. Local corrections that stand out against the general background (except for simple painting) should not be noticeable at a distance of 3 m from the surface

Technical inspection, acceptance certificate

Surfaces painted with waterless painting compounds must have a uniform glossy or matte surface. It is not allowed to show through the underlying layers of paint, peeling, stains, wrinkles, drips, visible grains of paint, clumps of film on the surface, brush and roller marks, unevenness, imprints of dried paint on the attached swab.

Surfaces painted with varnishes must have a glossy finish, without cracks, visible thickening, or traces of varnish (after drying) on ​​the attached swab

In places where surfaces painted in different colors meet, the curvature of lines, high-quality painting (for other types) in certain areas should not exceed, mm:

for simple painting - 5

for improved coloring - 2

curvature of panel lines and painting of surfaces when using different colors - 1 (per 1 m of surface)

When wallpapering surfaces, the following must be done:

with the edges of the overlapping panels facing the light openings, without shadows from them (when gluing with an overlap);

from panels of the same color and shades;

with precise fit of the pattern at the joints. Edge deviations should be no more than 0.5 mm (not noticeable from a distance of 3 m);

air bubbles, stains, omissions, additional gluing and peeling, and in places where openings adjoin the slopes, distortions, wrinkles, wallpapering of baseboards, trim, sockets, switches, etc. not allowed

When producing glass works:

the putty, after forming a hard film on the surface, should not have cracks and lag behind the surface of the glass and rebate;

the cut of putty at the point of contact with the glass must be smooth and parallel to the edge of the rebate, without protruding fasteners;

the outer chamfers of the glazing beads must fit tightly to the outer edge of the folds, without protruding beyond their limits and without forming depressions;

glazing beads installed on glass putty must be firmly connected to each other and to the binding fold; on rubber gaskets - the gaskets must be tightly clamped by the glass and fit tightly to the surface of the fold, glass and glazing beads, not protrude above the edge of the glazing bead, and have no cracks or tears;

when using any fastening devices, rubber profiles must be tightly pressed against the glass and the rebate groove, the fastening devices must correspond to the design and are tightly stored in the rebate grooves

Glass blocks installed on mortar must have smooth, strictly vertical and horizontal seams of the same width, filled flush with the surfaces of the glass units; the entire structure after installing the double-glazed window must be vertical, with tolerances not exceeding 2 mm per 1 m of surface

10 over the entire height

The surface of glass and glass structures must be free of cracks, gouges, holes, without traces of putty, mortar, paint, grease stains, etc.

Surfaces lined with blocks, slabs and tiles made of natural and natural stone must meet the following requirements:

surfaces must correspond to specified geometric shapes;

deviations should not exceed those given in table. 13;

the mating material and sealing of the seams, the dimensions and patterns of the cladding must correspond to the design;

surfaces lined with monochromatic artificial materials must have a uniform tone, with natural stone - a uniform color or a smooth transition of shades;

the space between the wall and the cladding must be completely filled with mortar;

horizontal and vertical seams of the cladding must be of the same type, single row and uniform in width;

the surface of the entire cladding must be hard;

chips in the seams are allowed no more than 0.5 mm;

cracks, stains, mortar drips, efflorescence are not allowed;

large-block elements made of natural stone must be installed on concrete;

fastening devices (fasteners) for cladding exposed to aggressive environments must be coated with anti-corrosion compounds or made of non-ferrous metal in accordance with the project

Finishing (cladding) of walls with factory-finished sheets must meet the following requirements:

There are cracks, air bubbles, scratches, stains, etc. on the surface of sheets and panels. not allowed;

the fastening of sheets and panels to the base must be strong, without instability (when lightly tapped with a wooden hammer, warping of the products, destruction of their edges and displacement of the sheets should not be observed);

the seams must be uniform, strictly horizontal and vertical; fastening devices and the distance between them, as well as the material, dimensions and design must correspond to the project;

deviations from the plane, horizontal and vertical should not exceed the standards given in table. 16

Note. Anti-corrosion coatings of building structures and technological equipment must meet the requirements of SNiP 3.04.03-85.

4. FLOORING CONSTRUCTION

GENERAL REQUIREMENTS

4.1. Before starting work on the construction of floors, measures must be carried out in accordance with the project to stabilize, prevent heaving and artificially stabilize soils, lower groundwater, as well as adjacent to expansion joints, channels, pits, drainage chutes, ladders, etc. Elements of edging coating must be completed before installation.

4.2. The soil base under the floors must be compacted in accordance with SNiP 3.02.01-87 “Earth structures, foundations and foundations”.

Vegetable soil, silt, peat, as well as bulk soils mixed with construction waste are not allowed under the soil foundation.

4.3. Installation of floors is allowed at the air temperature in the room, measured in the cold season near door and window openings at a height of 0.5 m from the floor level, and the laid floor elements and laid materials - not lower than, °C:

15 - when installing coatings made of polymer materials; this temperature must be maintained for 24 hours after completion of work;

10 - when installing floor elements from xylolite and from mixtures that include liquid glass; such a temperature must be maintained until the laid material acquires a strength of at least 70% of the design strength;

5 - when installing floor elements using bitumen mastics and their mixtures, which include cement; such a temperature must be maintained until the material acquires a strength of at least 50% of the design strength;

0 - when constructing floor elements from soil, gravel, slag, crushed stone and piece materials without gluing to the underlying layer or sand.

4.4. Before installing floors, the construction of which contains products and materials based on wood or its waste, synthetic resins and fibers, xylolite coatings, plastering and other work related to the possibility of moistening the coatings must be carried out in the room. When installing these floors and in the subsequent period until the facility is put into operation, the relative air humidity in the room should not exceed 60%. Drafts in the room are not allowed.

4.5. Floors resistant to aggressive environments must be made in accordance with the requirements of SNiP 3.04.03-85.

4.6. Work on the installation of asphalt concrete, slag and crushed stone floors should be carried out in accordance with SNiP 3.06.03-85 (Section 7).

4.7. Requirements for materials and mixtures for special types of floors (heat-resistant, radiation-resistant, spark-free, etc.) must be specified in the project.

4.8. Underlying layers, screeds, connecting layers (for ceramic, concrete, mosaic and other tiles) and monolithic coatings on a cement binder must be under a layer of constantly moist water-retaining material for 7-10 days after installation.

4.9. Standard use of xylolite floors, cement or acid-resistant concrete or mortar, as well as piece materials laid on layers of cement-sand or acid-resistant (liquid glass) mortar is allowed after the concrete or mortar has acquired the design compressive strength. Pedestrian traffic on these floors can be allowed no earlier than the concrete monolithic coverings have acquired a compressive strength of 5 MPa, and the solution of the layer under the piece materials has acquired a compressive strength of 2.5 MPa.

PREPARATION OF THE UNDERLYING FLOOR ELEMENTS

4.10. Dust removal of the surface must be performed before applying primers, adhesive layers for roll and tile polymer coatings and mastic compositions for solid (seamless) floors.

4.11. The surface layer must be primed over the entire surface without gaps before applying construction mixtures, mastics, adhesives, etc. (based on bitumen, tar, synthetic resins and aqueous polymer dispersions) to the underlying element with a composition corresponding to the material of the mixture, mastic or glue.

4.12. Moistening the surface layer of floor elements made of concrete and cement-sand mortar should be done before laying construction mixtures of cement and gypsum binders on them. Humidification is carried out until the final absorption of water.

CONSTRUCTION OF CONCRETE BASE LAYERS

4.13. Preparation, transportation and laying of concrete mixtures must be carried out in accordance with SNiP 3.03.01-87 “Load-bearing and enclosing structures” (Section 2).

4.14. When making concrete underlying layers using the vacuum method, the requirements of Table. 16.

Table 16

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Measuring, for every 500 m 2 surface, work log

Mobility of the concrete mixture - 8-12 cm

Vacuum pump vacuum - 0.07-0.08 MPa

Not less than 0.06 MPa

Measuring, at least four times per shift, work log

Duration of vacuuming - 1-1.5 minutes per 1 cm of underlying layer

The same, at each evacuation section, work log

STRUCTURE DEVICE

4.15. Monolithic screeds made of concrete, asphalt concrete, cement-sand mortar and prefabricated screeds made of wood fiber boards must be made in compliance with the rules for constructing coatings of the same name.

4.16. Gypsum self-leveling and porous cement screeds must be laid immediately to the calculated thickness specified in the project.

4.17. When installing screeds, the requirements of Table 1 must be met. 17.

Table 17

Technical requirements

Control (method, volume, type of registration)

Screeds laid over soundproofing pads or backfills, in places adjacent to walls and partitions and other structures, must be laid with a gap of 20 - 25 mm wide over the entire thickness of the screed and filled with similar soundproofing material:

monolithic screeds must be insulated from walls and partitions with strips of waterproofing materials

Technical, all junctions, work log

The end surfaces of the laid section of monolithic screeds, after removing the beacon or limiting slats, before laying the mixture in the adjacent section of the screed, must be primed (see clause 4.11) or moistened (see clause 4.12), and the working seam should be smoothed so that it is invisible

Smoothing the surface of monolithic screeds should be carried out under coatings on mastics and adhesive layers and under continuous (seamless) polymer coatings before the mixtures set

The same, the entire surface of the screeds, work log

Sealing the joints of prefabricated screeds made of fibreboards should be done along the entire length of the joints with strips of thick paper or adhesive tape 40 - 60 cm wide

Technical, all joints, work log

Laying of additional elements between prefabricated screeds on cement and gypsum binders should be done with a gap of 10-15 mm wide, filled with a mixture similar to the screed material. If the width of the gaps between the prefabricated screed slabs and walls or partitions is less than 0.4 m, the mixture must be laid over a continuous soundproofing layer

Technical, all clearances, work log

SOUND INSULATION DEVICE

4.18. Bulk soundproofing material (sand, coal slag, etc.) must be free of organic impurities. The use of backfills made from dusty materials is prohibited.

4.19. Gaskets should be laid without gluing to the floor slabs, and slabs and mats should be laid dry or glued with bitumen mastics. Soundproofing pads under the joists must be laid along the entire length of the joists without breaks. Tape spacers for prefabricated screeds of the size “per room” should be located in continuous strips along the perimeter of the premises close to the walls and partitions, under the joints of adjacent slabs, as well as inside the perimeter - parallel to the larger side of the slab.

4.20. When installing sound insulation, the requirements of Table. 18.

Table 18

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The size of the bulk soundproofing material is 0.15-10 mm

Measuring, at least three measurements for every 50-70 m2 of backfill, work log

Humidity of bulk material backfill between joists

No more than 10%

Width of soundproofing pads, mm:

Measuring, at least three measurements for every 50 - 70 m2 of floor surface, work log

under logs 100-120;

for prefabricated screeds of the size “per room” along the perimeter - 200-220, inside the perimeter - 100-120

The distance between the axes of the strips of soundproofing pads inside the perimeter of prefabricated screeds sized “per room” is 0.4 m

The same, at least three measurements on each prefabricated screed slab, work log

WATERPROOFING DEVICE

4.21. Pasted waterproofing using bitumen, tar and mastics based on them should be carried out in accordance with Section. 2, and polymer waterproofing - in accordance with SNiP 3.04.03-85.

4.22. Waterproofing from crushed stone impregnated with bitumen should be carried out in accordance with SNiP 3.06.03-85.

4.23. Before laying coatings, layers or screeds containing cement or liquid glass on it, the surface of bitumen waterproofing should be covered with hot bitumen mastic with dry coarse sand embedded in it in compliance with the parameters of the table. 19.

Table 19

REQUIREMENTS FOR INTERMEDIATE FLOOR ELEMENTS

4.24. The strength of materials that harden after laying must be no less than the design strength. Permissible deviations when installing intermediate floor elements are given in table. 20.

Table 20

Technical requirements

Limit deviations

Control (method, volume, type of registration)

The clearances between the two-meter control strip and the tested surface of the floor element should not exceed, mm, for:

Measuring, at least five measurements for every 50-70 m2 of floor surface or in one room of a smaller area in places identified by visual inspection, work log

soil bases - 20

sand, gravel, slag, crushed stone and adobe underlying layers - 15

concrete underlying layers for adhesive waterproofing and coatings on a layer of hot mastic - 5

concrete underlying layers for other types of coatings - 10

Screeds for polyvinyl acetate coverings, linoleum, rolls based on synthetic fibers, parquet and polyvinyl chloride boards - 2

screeds for coverings made of other types of slabs, end blocks and bricks laid over a layer of hot mastic, polyvinyl acetate cement-concrete coverings and for waterproofing - 4

screeds for other types of coverings - 6

Deviations of the element plane from the horizontal or a given slope - 0.2 of the corresponding room size

No more than 50

Measuring, at least five measurements evenly for every 50-70 m2 of floor surface in one smaller room, work log

DEVICE OF MONOLITHIC COATINGS

4.25. Monolithic mosaic coatings and coatings with a strengthened surface layer, arranged over concrete underlying layers, should be carried out simultaneously with the latter by embedding decorative, reinforcing and other bulk materials into a freshly laid evacuated concrete mixture.

4.26. When installing monolithic coatings, the requirements of Table. 21.

Table 21

Technical requirements

Control (method, volume, type of registration)

The maximum size of crushed stone and gravel for concrete coatings and marble chips for mosaic, polyvinyl acetate-cement concrete, latex-cement concrete coatings should not exceed 15 mm 0.6 coating thickness

Measuring - during the preparation of mixtures, at least three measurements per batch of filler, work log

Marble chips:

The same, at least three measurements per batch of filler, work log

for mosaic coverings must have a compressive strength of at least 60 MPa

polyvinyl acetate-cement concrete and latex-cement concrete not less than 80 MPa

Concrete and mosaic mixtures, which do not contain plasticizers, should be used with a cone slump of 2-4 cm, and cement-sand mixtures with a cone immersion depth of 4-5 cm. The mobility of mixtures should be increased only by introducing plasticizers

The same, one measurement for every 50-70 m2 of coverage, work log

Cutting monolithic coatings into separate cards is not allowed, with the exception of multi-color coatings, where separating cores must be installed between individual cards of different colors. Processing of joints between adjacent sections of a single-color coating must be carried out in accordance with clause 4.11 or 4.12

Rigid mixtures must be compacted. Compaction and smoothing of concrete and mortar in places of working seams should be carried out until the seam becomes invisible

Visual, entire surface of the monolithic coating, work log

Grinding of coatings should be carried out once the coating has reached a strength that prevents chipping of the aggregate. The thickness of the removed layer should ensure complete exposure of the texture of the decorative filler. When grinding, the surface to be treated must be covered with a thin layer of water or an aqueous solution of surfactants

Measuring, at least nine measurements evenly for every 50-70 m2 of coating surface, work log

Surface impregnation of coatings with fluates and sealing compounds, as well as finishing of concrete and cement-sand coatings with polyurethane varnishes and epoxy enamels should be carried out no earlier than 10 days after laying the mixtures at an air temperature in the room not lower than 10 ° C. Before impregnation, the coating must be dried and thoroughly cleaned.

Technical, entire surface coating, work log

CONSTRUCTION OF COATINGS FROM PLATES (TILES) AND UNIFIED BLOCKS

4.27. Slabs (tiles) of cement-concrete, cement-sand, mosaic concrete, asphalt concrete, ceramic, cast stone, cast iron, steel, natural stone and standardized blocks should be laid immediately after installing a connecting layer of mortar, concrete and hot mastics. The embedding of slabs and blocks into the interlayer should be carried out using vibration; in places inaccessible for vibration heating - manually. The laying and embedding of slabs and blocks should be completed before the mortar begins to set or the mastic begins to harden.

4.28. The basic requirements that must be met when constructing coverings from slabs and blocks are given in Table. 22.

Table 22

Technical requirements

Control (method, volume, type of registration)

Before laying on a layer of cement-sand mortar, porous slabs (concrete, cement-sand, mosaic and ceramic) must be immersed in water or an aqueous solution of surfactants for 15-20 minutes

Technical, at least four times per shift, work log

The width of the joints between the tiles and blocks should not exceed 6 mm when tiles and blocks are embedded into the interlayer manually and 3 mm when the tiles are vibrated, unless the design specifies a different width of the joints

Measuring, at least five measurements for every 50-70 m2 of coating surface or in one smaller room in places identified by visual inspection, work log

Mortar or concrete protruding from the seams must be removed from the coating flush with its surface before it hardens, hot mastic - immediately after cooling, cold mastic - immediately after protruding from the seams

Visual, entire coating surface, work log

The interlayer material must be applied to the back side of slag-ceramic slabs with a bottom corrugated surface immediately before laying the slabs flush with the protruding corrugation

Visual, at least four times per shift, work log

CONSTRUCTION OF COATINGS FROM WOOD AND PRODUCTS BASED ON IT

4.29. The joists under the coverings should be laid across the direction of light from the windows, and in rooms with a certain direction of movement of people (for example, in corridors) - perpendicular to the movement. The logs should be butted together end to end anywhere in the room with the joints in adjacent logs offset by at least 0.5 m. A gap of 20-30 mm wide must be left between the logs and the walls (partitions).

4.30. In floors on ceilings, the surface of the joists must be leveled with a layer of sand and tamped under soundproofing pads or joists along their entire width or length. The joists must touch the soundproofing layer, floor slabs or sand leveling layer with the entire lower surface, without gaps. Putting wooden wedges or supports under the joists to level them or resting the joists on wooden supports is prohibited.

4.31. Under the logs placed on posts in floors on the ground, wooden pads should be laid on two layers of roofing felt, the edges of which should be released from under the pads by 30-40 mm and secured to them with nails. The joist joints should be located on posts.

4.32. In doorways of adjacent rooms, a widened joist should be installed, protruding beyond the partition by at least 50 mm on each side.

4.33. Plank flooring boards, parquet boards connected to each other by side edges into a tongue and groove, and parquet panels using dowels must be tightly joined together. The reduction in the width of the coating products during bonding must be at least 0.5%.

4.34. All boards of the plank covering must be attached to each joist with nails 2-2.5 times longer than the thickness of the covering, and parquet panels - with nails 50-60 mm long. Nails should be driven obliquely into the face of the boards and into the base of the bottom cheek of the groove on the edges of parquet boards and parquet panels with the heads embedded. Hammering nails into the front surface of parquet boards and parquet panels is prohibited.

4.35. The joints of the ends of the boards of plank coverings, the joints of the ends and side edges with the ends of adjacent parquet boards, as well as the joints of the edges of adjacent parquet panels parallel to the joists should be placed on the joists.

4.36. The joints of the ends of the covering boards must be covered with a board (frieze) 50-60 mm wide, 15 mm thick, embedded flush with the covering surface. The frieze is nailed to the joist with nails in two rows with a pitch (along the joist) of 200-250 mm. Joining the ends without covering them with a frieze is allowed only in two or three wall covering boards; the joints should not be opposite the doorways and should be located on the same joist. When mating parquet boards, as well as parquet panels with sawn edges, a groove must be made on some of them, and a ridge on others, corresponding to those on the other edges.

4.37. Super-hard fibreboards, stacked and block parquet should be glued to the base with quick-hardening mastics on water-resistant binders, used in a cold or heated state. Adhesive mastic on the base under super-hard wood-fiber boards should be applied in strips 100-200 mm wide along the perimeter of the boards and in the middle zone with an interval of 300-400 mm. When laying out and cutting wood fiber boards, joining the four corners of the boards at one point is not allowed.

4.38. When installing coatings made of wood and products based on them, it is necessary to comply with the requirements of Table. 23.

Table 23

Technical requirements

Limit deviations

Control (method, volume, type of registration)

All logs, boards (except for the front side), wooden spacers laid on posts under the logs, as well as wood under the base of fiberboards must be antiseptic

Visual, all materials, inspection report of hidden work

The moisture content of materials should not exceed:

Measuring, at least three measurements for every 50-70 m2 of floor surface, work log

logs and gaskets

covering and base boards when laying inlaid and piece parquet, parquet boards and parquet panels

fiberboard covering

The length of the joined logs must be at least 2 m, the thickness of the logs resting with the entire lower surface on the floor slabs or soundproofing layer is 40 mm, the width is 80-100 mm. The thickness of the logs laid on separate supports (columns in floors on the ground, floor beams, etc.) should be 40 - 50 mm, width - 100-120 mm

Wooden spacers for joists in floors on the ground:

width - 100-150 mm, length - 200-250 mm, thickness - at least 25 mm

The distance between the axes of logs laid on floor slabs and for floor beams (when laying the coating directly on beams) should be 0.4-0.5 m. When laying logs on separate supports (columns in floors on the ground, floor beams, etc. ) this distance should be:

with a log thickness of 40 mm 0.8 - 0.9 m

with a log thickness of 50 mm 1.0 - 1.1 m

For large operating loads on the floor (more than 500 kg/m2), the distance between the supports for the joists, between the joists and their thickness should be taken according to the design

The length of the covering boards joined at the ends must be at least 2 m, and the length of parquet boards - at least 1.2 m

The thickness of the adhesive layer for stacked and piece parquet and super-hard wood-fiber boards should be no more than 1 mm

Measuring, at least five measurements for every 50-70 m2 of floor surface or in one smaller room, work log

Adhesive area:

Technical, with test lifting of products in at least three places per 500 m2 of floor surface, work log

parquet planks - at least 80%

fiberboards - at least 40%

DEVICE OF COATINGS FROM POLYMER MATERIALS

4.39. Before gluing, linoleum, carpets, roll materials made of synthetic fibers and polyvinyl chloride tiles must be allowed to sit until the waves disappear and are completely adjacent to the base; they must be glued to the underlying layer over the entire area, except for cases specified in the project.

4.40. Cutting of joined panels of rolled materials must be done no earlier than 3 days after the main gluing of the panels. The edges of the joined linoleum panels must be welded or glued after cutting.

4.41. In areas of heavy pedestrian traffic, the installation of transverse (perpendicular to the direction of movement) seams in coverings made of linoleum, carpets and roll materials made of synthetic fibers is not allowed.

4.42. When installing coatings made of polymer materials, the requirements of Table. 24.

Table 24

Technical requirements

Maximum deviations, %

Control (method, volume, type of registration)

The weight humidity of interfloor floor panels before installing coatings on them should not exceed, %:

Measuring, at least five measurements evenly for every 50 - 70 m2 of coating surface, work log

screeds based on cement, polymer cement and gypsum binders

fiberboard screeds

The thickness of the adhesive layer should be no more than 0.8 mm

When constructing continuous (seamless) coatings, mastic polymer compositions should be applied in layers 1 - 1.5 mm thick. The next layer should be applied after the previously applied layer has hardened and its surface has been dust-free

Measuring, at least five measurements for every 50 - 70 m2 of floor surface or in one smaller room, work log

REQUIREMENTS FOR THE READY FLOOR COVERING

4.43. The basic requirements for finished floor coverings are given in table. 25.

Table 25

Technical requirements

Control (method, volume, type of registration)

Deviations of the coating surface from the plane when checking with a two-meter control rod should not exceed, mm, for:

Measuring, at least nine measurements for every 50-70 m2 of coating surface or in one smaller room, acceptance certificate

earthen, gravel, slag, crushed stone, adobe and paving stone coverings - 10

asphalt concrete coverings, with a layer of sand, end coverings, cast iron slabs and bricks - 6

cement-concrete, mosaic-concrete, cement-sand, polyvinyl acetate concrete, metal cement, xylolite coatings and coatings made of acid-resistant and heat-resistant concrete - 4

coatings on a layer of mastic, end coatings, cast iron and steel plates, bricks of all types - 4

sand, mosaic-concrete, asphalt concrete, ceramic, stone, slag and metal - 4

polyvinyl acetate, plank, parquet and linoleum coatings, rolls based on synthetic fibers, polyvinyl chloride and super-hard fibreboards - 2

The ledges between adjacent coating products made of piece materials should not exceed, for coatings, mm:

from paving stones - 3

brick, end, concrete, asphalt concrete, cast iron and steel slabs - 2

from ceramic, stone, cement-sand, mosaic-concrete, slag-and-sand slabs - 1

plank, parquet, linoleum, polyvinyl chloride and super-hard fiber boards, polyvinyl chloride plastic - not allowed

Recesses between coverings and floor edging elements - 2 mm

Measuring at least nine measurements for every 50-70 m2 of coating surface or in one room of a smaller area, acceptance certificate

Deviations from the specified slope of coatings - 0.2% of the corresponding room size, but not more than 50 mm

Deviations in coating thickness - no more than 10% of the design

The same, at least five measurements, acceptance certificate

When checking the adhesion of monolithic coatings and coatings made of rigid tile materials with underlying floor elements by tapping, there should be no change in the nature of the sound

Technical, by tapping the entire floor surface in the center of the squares on a conventional grid with a cell size of at least 50 ´ 50 cm, acceptance certificate

Gaps should not exceed, mm:

Measuring, at least five measurements for every 50-70 m2 of coating surface or in one smaller room, acceptance certificate

between the boards of the plank covering - 1

between parquet boards and parquet panels - 0.5

between adjacent strip parquet plans - 0.3

Gaps and cracks between skirting boards and floor coverings or walls (partitions), between adjacent edges of linoleum panels, carpets, rolled materials and tiles are not allowed

Visual, entire floor surface and joints, acceptance certificate

The coating surfaces should not have potholes, cracks, waves, swelling, or raised edges. The color of the coating must match the design

The same, the entire floor surface, acceptance certificate

1. General Provisions. 1

2. Insulating coatings and roofs. 2

General requirements. 2

Preparation of foundations and underlying insulation elements. 3

Installation of insulation and roofing from roll materials. 5

Installation of insulation and roofs made of polymer and emulsion-bitumen compositions. 6

Installation of insulation from cement mortars, hot mix asphalt, bitumen perlite and bitumen expanded clay. 7

Carrying out thermal insulation work using soft, rigid and semi-rigid fiber products and constructing thermal insulation cover shells from rigid materials. 8

Installation of thermal insulation from slabs and bulk materials. 8

Construction of roofs made of piece materials. 9

Insulation and roofing parts made of metal sheets. 10

Requirements for finished insulating (roofing) coverings and structural elements. 10

3. Finishing work and protection of building structures and technological equipment from corrosion (anti-corrosion work) 12

General provisions. 12

Surface preparation. 14

Production of plastering and stucco works. 16

Production of painting works. 17

Production of decorative finishing works. 17

Production of wallpaper works. 18

Production of glass works. 19

Production of facing works. 19

Installation of suspended ceilings, panels and slabs with front finish in building interiors. 22

Requirements for finished finishing coatings... 22

4. Installation of floors. 25

General requirements. 25

Preparation of underlying floor elements. 26

Construction of concrete underlying layers. 26

Screed device. 26

Soundproofing device. 27

Waterproofing device. 28

Requirements for intermediate floor elements. 28

Installation of monolithic coatings. 29

Installation of coverings from slabs (tiles) and standardized blocks. thirty

Installation of coatings made of wood and wood-based products. thirty

Construction of coatings made of polymer materials. 32

Requirements for the finished floor covering. 33

BUILDING REGULATIONS

INSULATING AND FINISHING COATINGS

SNiP 3.04.01-87

STATE CONSTRUCTION

USSR COMMITTEE

Moscow 1988

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidates of technical sciences N. N. Zavrazhin - topic leader, V. A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I. P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences D. B. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences Prof. E. D. Belousov, Candidate of Technical Sciences G. S. Agadzhanov), SKTB Glavtunnelmetrostroy of the Ministry of Transport and Construction of the USSR (Candidate of Technical Sciences V. V. Krylova , V. G. Golubova), Department of Soyuzmetrospetsstroy of the Ministry of Transport and Construction of the USSR (A. P. Levina, P. F. Litvina), NIIZHB of the State Committee for Construction of the USSR (Doctor of Technical Sciences, Prof. F. M. Ivanova).

INTRODUCED BY TsNIIOMTP Gosstroy USSR.

PREPARED FOR APPROVAL by the Department of Standardization and Technical Standards in Construction of the USSR State Construction Committee (D.I. Prokofiev).

With the entry into force of SNiP 3.04.01-87 “Insulating and finishing coatings”, SNiPs lose their validity III-20-74*, SNiP III-21-73*, SNiP III‑ V.14-72; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using a regulatory document, one should take into account the approved changes to building codes and rules and state standards published in the journal “Bulletin of Construction Equipment”, “Collection of Amendments to Building Codes and Rules” of the USSR State Construction Committee and the information index “USSR State Standards” of the USSR State Standard.

State

Building regulations

SNiP 3.04.01-87

Construction Committee of the USSR (Gosstroy USSR)

Insulating and finishing coatings

Instead:

SNiP III-20-74*;

SNiP III-21-73*;

SNiP III-B.14-72;

GOST 22753-77;

GOST 22844-77;

GOST 23305-78

1. GENERAL PROVISIONS

l.l. These building codes and regulations apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to the special operating conditions of buildings and structures.

1.2. Insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - in accordance with the standard). Replacement of materials, products and compositions provided for by the project is allowed only by agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can begin only after the execution of an act (permit) signed by the customer, representatives of the installation organization and the organization performing thermal insulation work.

1.4. The installation of each insulation element (roof), floor, protective and finishing coatings should be carried out after checking the correct execution of the corresponding underlying element and drawing up an inspection report for hidden work.

1.5. With appropriate justification, in agreement with the customer and the design organization, it is allowed to prescribe methods for performing work and organizational and technological solutions, as well as establish methods, volumes and types of registration of quality control of work that differ from those provided for by these rules.

GENERAL REQUIREMENTS

2.1 . Insulation and roofing work can be performed from 6 0 to minus 30 ° From the environment (work with the use of hot mastics - at an ambient temperature of at least minus 20 ° C, using water-based compositions without antifreeze additives, not less than 5 ° WITH ) .

ass Do not make seams between prefabricated slabs;

will suit b temperature-shrinkable seams;

install embedded elements;

plaster sections of vertical surfaces of stone structures to the height of the junction of the rolled or emulsion-mastic roofing carpet and insulation.

2.3. Insulating compounds and materials must be applied in continuous and uniform layers or in one layer without gaps or sagging. Each layer must be laid on the hardened surface of the previous one, leveling the applied compounds, with the exception of paint ones. When preparing and preparing insulating compositions, the requirements of Table. 1 .

Table 1

Technical requirements

Limit deviations

Control (method, volume, type of registration)

Bitumen and tar (pitch) must be used cleaned of impurities and dehydrated. Heating should not exceed ° WITH:

bitumen - 180

tar (pitch) - 140

± 5 %

± 7 %

Measuring, periodic but at least 4 times per shift, work log

Fillers (aggregates) must be sifted through a sieve with cell sizes, mm:

for sand - 1.5

for dusty ones - 2

for fibrous - 4

Same

Permissible moisture content of fillers (aggregates):

for sand

for compositions with sealing additives

for other compounds

Up to 2%

up to 5%

until 3 %

Measuring, periodic, at least 4 times per shift, work log

Temperature of emulsions and their components, ° WITH:

bitumen - 110

emulsifier solution - 90

latex (when introduced into the emulsion) - 70

10 ° WITH

7 ° WITH

Minus 10 ° WITH

The same, at least 5-6 times per shift, work log

Uniformity of bitumen distribution in bitumen perlite and bitumen expanded clay - 90%

± 2 %

Same

The compaction coefficient of bitumen perlite and bitumen expanded clay under pressure of 0.67-0.7 MPa is not less than 1.6

Temperature when applying mastics, ° WITH:

hot bitumen - 160

hot tar - 130

cold (in winter) - 65

20 ° WITH

10 ° WITH

5 ° WITH

Installation of insulation dispersedly reinforced with glass fiber (fiberglass fibres):

fiber sizes - 20 mm

The ratio by weight of aluminous cement to Portland cement is 90: 10

20 mm

Up to 80:20

Measuring, periodic at least 16 measurements per shift (every 0.5 hours of work), work log

Heavy concrete for constructing roofs without an insulating coating (roof) must contain:

plasticizing and air-entraining additives, fillers made of fractionated sand and coarse crushed stone;

Portland cement - hydrophobic, containing no more than 6% calcium aluminate;

crushed stone of igneous rocks or gravel with a temporary resistance of at least 100 MPa in a water-saturated state; granulometric composition of crushed stone, mm:

5-10

10-20

sand of the protective layer, size modulus - 2.1 - 3.15

25-50 %

75-50 %

Measuring, periodic, at least 4 times per shift, work log

Gravel and other frost-resistant mineral materials should be sorted and washed

Same

PREPARATION OF FOUNDATIONS AND UNDERLYING

INSULATION ELEMENTS