Where to start renovating a bathroom - the sequence of work. Bathroom renovation: estimate, specifics of the room, full cycle of work Do-it-yourself turnkey bath

So, the moment has finally arrived. Moral fatigue just the type of premises for daily sanitary and hygienic procedures, not to mention visiting, exceeded all future costs. We need to start renovating the bathroom. But where to start and how to plan the work?

Planning actions for bathroom renovation

The first thing to do when renovating a bathroom and toilet is to find out what kind of work the apartment owners can do with their own hands, and which ones will require the involvement of specialists.

If possible, assess the condition of communications and screeds, although this can be difficult to do before dismantling. Make up full list works and their sequence. When contacting professional craftsmen you need to ask to see samples of renovated objects and do not hesitate to ask questions.

Depending on the budget, they determine whether it will be an inexpensive lightweight redecorating or a major refurbishment of a premium bathroom.

Sketch and design of the future bathroom

Taking into account the size of the room and personal preferences, they decide what to install in the apartment. If the area is small, you may have to limit yourself to a shortened or sit-down bathtub or shower.

In a spacious bathroom, on the contrary, it is appropriate to think about installing a jacuzzi and even a mini-sauna. Options that do not work not only due to size, but also design features, cut off.

Advice! After measuring the room, you need to transfer its plan to paper or a computer and try to find the most convenient location of plumbing and washing machine.

For design development, it is better to turn to specialists in this field, but if there is a lack of funds, there is a chance to master it yourself. There are enough images and videos on the Internet with examples of repairs and detailed description. Particular attention is paid to decorating those details that should not be conspicuous.

Even before starting repairs, it is necessary to think through the lighting and electrical system. Don't limit yourself to just one lamp. Multiple lighting sources and additional lighting mirrors will create a relaxed and peaceful atmosphere.

Electrical installation items include a socket for a hair dryer and electric razor, a washing machine, a switch for a mirror and a duct fan.

Furniture, faucets, fittings and lamps should fit organically into the overall picture and create a feeling of a single style. An incorrect selection can negate all the most talented work of designers, and one single successful detail will make the space around you sparkle in a new way.

Selection of materials and plumbing

The main requirement for materials for bathroom renovation is moisture resistance and corrosion resistance, and for electrical equipment - waterproof design. Other important condition– high-quality plumbing. Unreasonable savings threaten not only loss of appearance, but also equipment failure.

The main materials that can be used in the case of bathroom renovation are:

  • pipes - there are metal-plastic, polypropylene, PVC, copper, stainless steel;
  • tiles, mosaics, PVC panels are used for walls, decorative plaster, panels, coloring, Various types wallpaper (vinyl, liquid, glass wallpaper);
  • ceilings are finished PVC panels, paint, plasterboard, make slatted suspended ceilings, suspended ceilings;
  • floors – tiles, self-leveling floors with a 3D pattern, linoleum, cork, laminate, parquet;
  • partitions - blocks of cellular concrete, gypsum slabs, glass blocks;
  • the bathtub after renovation can be new or restored acrylic liner, liquid acrylic;
  • toilet – compact toilet, with a hinged or hidden cistern, with wall mounting, rimless, anti-splash system, different systems flush control;
  • washbasin – built into the bedside table, with a “tulip” leg;
  • lamps – energy-saving, halogen, LED, LED panels.

In case of replacement or upgrading of wiring electrical wire It is preferable to take NYM brands. Depending on the chosen bathroom renovation idea, a set finishing materials may change. An interesting option is a combination of contrasting colors.

Finishing materials are purchased with a margin of 10–15%, since the shade of different batches of goods does not completely match and subsequently it will be difficult to find a replacement. If you shop in one store, you can count on a discount. Receipts are not thrown away in order to exchange purchased goods in case of defects.

Procedure for vacating the bathroom

When the design is thought out, the materials are selected, the question arises, where to start renovating the bathroom with your own hands, with what actions? The answer is simple - they begin to vacate the premises.

After the water supply is turned off, they are taken out of the room old bath, remove plumbing fixtures and accessories, dismantle the plumbing cabinet. The water and sewer pipes are dismantled, and the entrance to the sewer riser is closed with a plug. Without this, comprehensive repairs will not be possible.

The heated towel rail is cut off and, taking into account its transfer to another place, a new insert is made with bends into the riser of the hot water supply pipe. Or they completely replace the common sections of the water supply system that are in disrepair.

It is not possible to cut off the heated towel rail and replace the risers on your own; a management company is hired to carry out this work.

Important! Old utilities in the apartment must be replaced, otherwise after a while leaks will begin and the repair will go down the drain.

When remodeling or replacing flimsy structures, doors are removed and non-load-bearing wall partitions are demolished. Clean off old wall and ceiling coverings. The wallpaper is pre-soaked and the paint is softened construction hairdryer, then act with a spatula. The whitewash is washed off with water, and the facing structures are dismantled.

It is also better to knock down tiles with a plaster layer. Now in production adhesive mixtures, allowing tiling work to be carried out on the previous cladding, but this reduces the volume of the bathroom.

Concrete screed in good condition can be left, except for cases when it is planned to install a “warm floor” system or when it is necessary to get rid of a high threshold and bring the floors in the bathroom and corridor to the same level.

Construction of partitions and leveling of bases

To replace the demolished partitions, new ones provided for by the project are erected, as well as false walls for zoning space, niches, and shelves. At the same time, the ventilation shaft is restored if it is damaged.

Important! Doorways are formed so that the frame fits into them standard sizes. Otherwise you will have to pay more for individual order doors or remodel.

For cladding on a frame or suspended ceilings, preliminary alignment of the walls and ceiling is not required. An additional advantage of such structures is that they can hide communications without gating, which will facilitate bathroom renovations.

If leveling is still necessary, the surface is primed, beacons are placed and plaster is applied. In areas affected by the fungus, first remove all layers down to the base and treat with an antiseptic. The plane of the finished surface is checked using the diagonal rule.

After plastering, the screed is poured along the beacons on the floor. Simultaneously with this operation, a “warm floor” system is installed. If you decide to leave old screed, it is sanded and leveled thin layer self-leveling floors.

Laying new pipes and electrical wiring

They start cutting walls for pipes and electrical wiring, thoroughly equipped with respiratory, vision and hearing protection. In the lower part of the wall, where the pipes run in a single bundle, communications are usually put away in a box. There is no need to hide pipes in grooves if they are covered from above with a bathtub or shower tray.

Advice! It is very convenient to make a recess in the wall under the hoses of the washing machine in order to move it closer.

To prevent corrosion, metal water risers are painted and packaged in thermal insulation material to protect them from condensation and extend their service life. The sewer riser is replaced using management company. To prevent the noise of water drained by neighbors from disturbing the apartment, the sewer riser is lined with sound insulation.

Before wiring, a frame installation system is installed in the plumbing cabinet for hidden installation toilet cistern, which saves some space. After connecting the hot and cold water supply pipes to the collector with the installation of meters and sensors, the strength and tightness of the connections are checked - pressure testing. This mandatory procedure during major repairs.

Important! Installation of hot and cold water supply pipes is carried out taking into account the location of the corresponding inlets on the mixer.

Electrical wiring is supplied to the locations of electrical installation products and equipment. For electrical safety, the wires are hidden in corrugation and a grounding loop is made. To ensure that electrical wiring is done correctly, the work must be carried out by an experienced person.

After laying the communications, the grooves are sealed and the walls of the plumbing cabinet with a hidden inspection hatch are erected. Depending on where it is more convenient to open, forward or sideways, choose one of two hatch design options - sliding or hinged. For the period before installation new plumbing They put in an old toilet.

Plumbing installation

A major bathroom renovation is not complete without replacing the plumbing. The floors are covered with coating or penetrating waterproofing. If they decide not to change the bathtub, they do a restoration. Apply at the edge of the bathtub silicone sealant. Then the bathtub is moved close to the wall and leveled horizontally for normal drainage.

Advice! You can push the edges of the bathtub adjacent to the walls into the groove made in advance.

After connection, the joint is filled with a waterproofing solution. It firmly fixes the bathtub and seals the seam at the junction with the tile, preventing it from cracking.

The bathtub is grounded, connected to the sewer system, a mixer is installed and filled with water to check the functionality and tightness of the siphon and drain-overflow system. The space under the bathtub is covered with a screen.

Screen installation options:

  • non-removable. They are laid out from foam blocks or assembled on a plasterboard frame with an invisible hatch in the drain area. A recessed niche for the feet is left below;
  • removable. They buy it ready-made and install it after laying the tiles. The removable hatch looks less aesthetically pleasing, but the space under the bathroom can be used to store all sorts of household items.

The toilet and washbasin with faucet are installed later, after finishing is completed.

The plumbing is connected to the sewer outlet and water supply and fixed to the floor or wall, not forgetting to level it horizontally.

The pipes under the washbasin are masked with a furniture cabinet, a “tulip” leg, and a tabletop pre-laid out of foam blocks.

A seat with a lid is installed on the toilet. Classic white sanitary ware looks beautiful.

Room decoration

Finishing in case of cosmetic and major repairs may vary greatly. The instructions for tiling are as follows.

Laying the tiles begins from the top edge of the bathtub. Since the surface of the side is not very smooth, it is usually impossible to maintain the same width of the seam along the entire border with the bathroom. The tiles have to be cut very evenly or the seam must be covered with a corner or plinth.

Advice! A perfectly even seam is obtained when cutting with a mechanical tile cutter. Electric tile cutter With diamond blade makes chips on the surface.

Cutouts are made in places where communications are supplied. The socket boxes are placed so as not to hit the joint. On external corners The tiles are cut at an angle of 45°. Fitting and laying the bottom row wall tiles performed only after tiling the floor.

When laying, they try to remove the cut tiles from view and hide them in corners, under the bathtub or boxes. For precise fitting, manufacturers offer borders, friezes, and inserts, but they are much more expensive. More affordable option– use scraps of tiles of a different color.

After installation is completed, the seams are filled with epoxy resin-based grout, and excess grout is removed immediately. Once frozen, the puffer is more difficult to clean and can scratch the surface.

Installation of PVC panels is simpler than working with tiles and takes much less time. PVC panels are mounted on guides made of wooden slats, metal or plastic profiles hidden fastenings - clamps. The wood is pre-treated with antiseptics.

The cut ends are hidden at the top and bottom with starting strips. External and internal corners are installed in the corners. Particular attention is paid to the vertical evenness, especially of the first plank, and the alignment of the pattern. The finishing process is completed by installing a tension or suspended ceiling.

The last stage of repair

At the final stage, the attributes of the bathroom are installed: mirrors, shelves, cabinets, soap dishes, holders, racks. Attach hooks and towel racks and other small fittings. Connect the heated towel rail to the outlets hot water, installing a curtain for the bathroom.

Niches for lamps are cut in suspended ceilings, electrical installations and lighting fixtures are connected to the wires. They put ventilation grates And decorative overlays. The renovation of the bathroom and toilet is completed by installing doors.

Let's look at how to renovate a bathroom yourself. What tools do we need for this? What difficulties await us and how to overcome them. How not to miss important points when renovating a bathroom. Why high-quality DIY repairs will not always be cheaper than repairs by hired workers.

Like any other construction and renovation project, you should start with a design and estimate. We need to figure out what exactly we want to see in the renovated bathroom. Compose detailed list necessary:

  • furniture
  • plumbing
  • Appliances

Then you should estimate the arrangement of all of the above, taking into account access to communications. For example, it is not always possible to lay a sewer in the place where you would like to install a washing machine or shower while maintaining the required slope of 2% (2 cm per 1 meter of length). Therefore, take this moment into account in advance so as not to suffer in the future with constant sewer blockages.

After you have “put” everything in its place, think through in detail the design that you would like. And start estimating.

If you're on a budget, you can start doing your own bathroom renovation. To do this, we need to understand what tool we need.

Essential Tool for Bathroom Renovation

Usually, those who start repairing with their own hands already have some kind of tool in their arsenal. If you are going to purchase necessary tool to renovate a bathroom from scratch, we strongly recommend that you think about whether it would be cheaper to hire workers with their own tools? Because the cost of work is usually 50% of the cost of materials for finishing and communications, and the cost of tools can even exceed this amount. Tool for quality repairs the bathroom is not cheap. And if in the future you do not plan to carry out independent repairs, it will be a waste of money. Consider leasing or later selling the instrument. So, what do we need:

  • hammer drill with wide chisel, drills, mixer attachment
  • groove tool
  • soldering iron for plastic pipes
  • tile cutter (if you plan to finish with tiles)
  • spatulas
  • diamond crowns
  • electrical work kit
  • regular set of plumbing tools

Work order

First, you need to turn off the power and water. Then remove all furniture and fixtures from the bathroom. But don't rush to throw it away. If you have a good but old cast iron bath, consider this option.

After cleaning the room, cover the doors tightly with film or cloth and begin cleaning the ceiling, walls and floor. Old whitewash you need to wash it off, remove the paint with a drill with an attachment or a hair dryer. The tiles are cut using a hammer drill with a wide chisel. Don't forget about construction glasses, a respirator and gloves. Dust and small chips of tiles are very dangerous.

Take a good look old plaster and floor screed. They must be strong, fairly even and without cracks. Otherwise they will have to be replaced. When replacing floor screed, consider installing . Small irregularities and flaws can be repaired by puttying tile adhesive, having previously primed the surfaces well.

Sewerage

Let's start replacing communications. First we deal with the sewerage. Here important point is the insulation of risers and maintaining the slope when horizontal wiring pipes Be sure to insulate the sewer riser with foamed polypropylene, because condensation can seriously damage your repairs in the future. Don't forget, by sewer riser coming warm air. And the riser is usually “sutured up” various partitions, screens, etc. This significantly impedes the external ventilation of the riser. Therefore on outside pipes, condensation forms, which then leads to moisture, dirt, rot, and fungus. Another advantage of insulation will be increased sound insulation. Let us remind you that the slope of the sewer pipe in the horizontal plane should be 2% (2 cm per 1 meter of length). This slope makes it possible to wash away debris through the pipe in a stream of water. With a greater slope, the water will flow away faster than the debris, and with a smaller slope, the debris will stagnate.

Water pipes

Then we change water pipes. Modern repairs involve hidden pipe routing. Therefore, you will have to tinker with the grooves for the pipes. Provide a cabinet or niche with a door near the water riser to allow you to check water meters and locate the main shut-off valves there. In this case, you can always easily turn off the water in the bathroom.

Important point: when you have laid the pipes under the mixer on the wall, connect any old mixer(or a carefully closed new one) to the outlet and plaster the groove with the pipes. Or use a special mounting strip for fixing fittings. This will secure the ends in the required plane. So that it doesn’t happen later that they will “look” in different directions.

Electrics

The next step is to install the electrical wiring. Choose wires with good insulation; check this point with a consultant in the store. All sockets and lamps must also be made specifically for rooms with high humidity. Under no circumstances should you install “regular” sockets and switches. Fortunately, now the choice makes it easy to find suitable option. Provide protection for the new wiring from short circuits and the ability to disconnect the bathroom separately from the rest of the home.

Ceiling

Then we start working on the ceiling. At modern renovations In old Khrushchev-type apartments, it is not uncommon for the ceiling level to drop. They make it either hanging or built into it Spotlights etc. The main thing here is not to forget that the ceiling cannot be made of regular drywall and what should not be closed vent. Ventilation is very important in the bathroom. We take into account that the air flow into the bathroom should be at the opposite end from the exhaust vent. Usually, the holes at the bottom serve as “inlets” front door. Consider deleting humid air from the room on the opposite side. Don't forget that if you have a small bathroom, e.g. 3-6 sq. meters, then you will need forced ventilation. Buy and install an exhaust fan. At larger size premises, forced ventilation is installed in case of insufficient draft in the air duct.

Floor

After the ceiling we move to the floor. If you need a new screed, we make it. If possible, we insulate it. We put flooring. The most common coating is still ceramic tiles. When laying it, they are guided by the principle that installation should begin from the most visible place. This is usually the entrance. So that the tile trims go under the bathtub or furniture. But tiles are not the only option for finishing a bathroom. Moisture-resistant wood varieties such as teak and larch are now popular. It is of course expensive, but very beautiful.

Walls

Then we move on to the walls. Before finishing the walls, be sure to prime them. If you are finishing the walls with tiles, then here, as in the case of the floor, installation begins from the most noticeable place. If you decide to paint the walls, then choose moisture-resistant paint that does not allow steam to pass through. Before painting, cover the wall with penetrating waterproofing. If you have chosen plastic or other wall panels, then also take care of waterproofing. Keep in mind that the frame of the sheathing under the panels cannot be made of wood. IN covered with panels space, the tree will rot very quickly. In addition, it will be a source of fungus and other infections in your bathroom. Choose a galvanized metal profile. Or glue the panels with special sealants and adhesives, like ““.

Installation of furniture and plumbing

The next step is to install the furniture and connect the plumbing. WITH new technology Handle with care and remember to read the instructions before installation. After installation, we do a test run and check for leaks, proper operation devices, etc.

If everything is ok, congratulations! You have successfully completed your DIY bathroom renovation. And this is not an ordinary event. We hope that our instructions helped you organize your thoughts, and perhaps taught you something. Please share your experience in the comments to the article. We are very interested in how you managed to renovate the bathroom yourself and what came out of it.

In any type of room renovation, there is a certain sequence that allows you to break down all the work into separate stages, analyze each stage in detail, and accurately calculate the amount consumables and display the total amount of repairs. As in other rooms, it is necessary to follow the sequence of renovations in the bathroom, since violation of the algorithm of actions can lead to unexpected financial costs, and sometimes to repeated remodeling. Often, if the sequence of work is not followed, you may encounter damage to the finishing material from construction dust and dirt. In order for the work to be done quickly and efficiently, you need to divide the entire process into separate stages and study each in detail.

Sequence of repair work

The first question that inevitably arises for any novice master is where to start renovating a bathroom. In order to make the task easier, we will take the standard algorithm as a basis and analyze its sequence in detail. Step-by-step repair instructions will consist of the following points:

  • drawing up a project plan;
  • dismantling plumbing fixtures and old finishing materials;
  • surface preparation;
  • replacement of communication systems;
  • preliminary finishing of the premises;
  • finishing cladding;
  • installation of appliances and plumbing elements;
  • general cleaning of the premises.

The listed stages of work must be performed in strict sequence, which is indicated in the list, otherwise there is a high probability of damage facing material.

Drafting

At the stage of creating a project, it is important to remember that the bathroom is considered quite complex from a technical point of view, since it contains a large number of various communications, and the bathroom renovation plan should be as detailed as possible, indicating all the main dimensions. In order to avoid any troubles as a result of the work, experts recommend drawing up a general plan of the room, and then on separate sheets of paper making detailed calculations for each surface separately, describing the stages of bathroom renovation. This instruction must contain a scale drawing of the floor, ceiling and each wall with exact dimensions, and it is also necessary to indicate in advance, down to the millimeter, the exact location of such elements as:

  • wash basin;
  • mirror;
  • electric hand dryer;
  • towel dryer;
  • lighting;
  • sockets and switches;
  • bath and toilet;
  • furniture and accessories;
  • washing machine, bidet, urinal, water filters and other plumbing items that require the installation of additional water supply and sewerage lines.

Also, the bathroom renovation plan must contain records of the power of all electrical appliances and the required cross-section of the electrical cable to support them.

Dismantling of plumbing fixtures and finishing materials

After drawing up a plan and a preliminary estimate, you can begin work. Bathroom renovations always begin with the dismantling of all plumbing elements. It is important to remember that you first need to remove the furniture from the room and all other bulky elements that will occupy the workspace. This will not only free up space, but will also help protect furniture and plumbing from damage during dismantling old tiles and preparation of the premises.

Carrying out step by step repair bathroom, it is important to remember that when dismantling the main task is not to quickly break it, but to carefully remove it old finishing without causing much damage to the base, since you will need to repair all this damage later. As a result, the room should look like the photo above.

Also, the procedure for carrying out renovations in the bathroom at this stage involves gating the walls for laying electrical cables to consumers, drilling holes for sockets and switches.

Replacing old communications with new ones

In this area of ​​work, it is necessary to dismantle all old pipelines and electrical wiring. Next, the installation of new plumbing is carried out step by step, starting from the central water supply system to each consumer according to the plan. Then the sequence of bathroom renovations involves installing sewer main and styling electrical wires into pre-made grooves in the walls. At this stage of work, all additional units of the water supply system, such as filters and sedimentation tanks, are connected.

Many people mistakenly believe that they can break the sequence of bathroom renovations and not replace the old ones. metal pipes on plastic, but experts do not recommend leaving the old plumbing fixtures, since the pipes are sewn up under the lining and in case of a leak, you will have to disassemble everything again.

Preliminary finishing of the room

Following the sequence of work in the bathroom, after installing plumbing, sewerage and all additional elements, rough or preliminary finishing follows step by step. If you plan to use plasterboard to level the walls, then first you need to equip the floor surface, lay waterproofing and fill the screed. If the stages of renovation in the bathroom are designed to use putty or plaster to level the surface, then the floors are put aside last.

Waterproofing of the room is achieved by treating the floor surface epoxy resins or use thick polyethylene film before pouring the screed.

Further, the procedure for renovating a bathroom at this stage involves the construction of boxes to hide plumbing, the installation of plasterboard partitions and the construction of a frame for a suspended or suspended ceiling. Upon completion pre-finishing The premises are cleared of construction debris.

Finish lining

The procedure for renovating a bathroom at the finishing stage involves installing the facing material that was chosen to decorate the room. Usually the first thing to do is lay them on the walls. ceramic tiles, then lay out the floor covering and already final stages work is devoted to installing a suspended or suspended ceiling. It is not for nothing that the procedure for renovating a bathroom leaves finishing the ceiling as an afterthought.

If the preparation of the bathroom for renovation has been carried out correctly and the surface is leveled, then laying wall tiles usually begins with top corner, this allows you to significantly save material and place all pieces and remnants in the lower part of the room, where they are least noticeable. In order not to damage the suspended or suspended ceiling, it is put aside last. After finishing covering all surfaces, stage-by-stage repair The bathroom is moving to the stage of installing equipment and plumbing.

Installation of plumbing and electrical appliances

The final stage of renovation is considered the most interesting, since at this stage the room already takes on its normal appearance and gradually begins to please the owners. If the step-by-step renovation of the bathroom was followed, then now we have a fully finished room with plumbing, sewerage outlets and wires sticking out of the wall.

Now the toilet, bathtub, electrical devices, lighting elements, mirror and all additional fittings along with the furniture. If the sequence of renovation in the bathroom has been followed, then upon completion of the installation of all elements and partial decoration, you can safely carry out general cleaning and enjoy a chic and cozy bathroom. Additional information you can get it by watching the video in the article.

After reading this material, you will have in your hands complete step-by-step instructions for renovating a bathroom, compliance with which will guarantee high-quality and quick completion of all assigned tasks.

The bathroom is a special room in an apartment or private house. Its repair requires a careful approach. Due to high humidity and temperature changes, all finishing work must be carried out at a high level.

If you have the financial opportunity and free time, start a capital investment do-it-yourself repair It will be quite possible. Below you will find the main stages of a DIY bathroom renovation.

Types of repair work

Repairs can be carried out in a planned or unplanned manner. In the first case, two options are possible - cosmetic and major, and the latter requires thorough preparation.


The cosmetic option is cheaper, but it can only be carried out if there is no mold or mildew in the room, and the plumbing system is functioning properly.

Unplanned work is a consequence of an unforeseen situation (pipeline break, flooding due to the fault of neighbors).

Another reason for not acting according to plan could be a suddenly discovered defect in a component, for example, when installing a new bathtub.

Development of room design and action plan

Before you begin the renovation, you need to imagine what the bathroom should look like in the future, what color scheme choose for her. Pastel colors or a combination of them will be traditional.

If difficulties arise at this creative stage, it makes sense to study the variety of photos beautiful renovation in the bathroom. After this, you need to think about what materials will be used in the future.

The bathroom is finished using:


Using a tape measure, you should carefully measure the length, width and height of the room, and calculate its area. The data obtained will allow us to calculate required quantity construction and finishing materials. The location of plumbing fixtures is thought out in advance, since rearrangements will be much more difficult to carry out later.

If the experience repair work no, then it would be useful to purchase relevant literature on repairs. Presented in it step by step instructions about how you can make a bathroom with your own hands will fill the missing knowledge, and experience will come with time.


Purchase of plumbing fixtures and finishing materials

The choice of plumbing equipment and materials is as follows important stage on the way to creating comfort in the bathroom. Immediately before purchasing a bathtub, toilet, shower cabin and other equipment, you should check their dimensions.

It is better to purchase finishing materials and working tools in full and in one store, if everything you need is available. At major purchase you can get a good discount.

Dismantling works

Any room requires preparation before renovation. The bathroom is no exception. If replacing a bathtub or sink is not intended, in order to preserve its integrity, it is better to dismantle it.

Old tiles, ceiling and wall coverings are removed. Painted areas are completely cleaned. The new coating and adhesives must be applied to a carefully prepared surface.

Pipes, wiring and other communications

After dismantling the old coating, the stage of replacing the pipes begins. In houses with an older layout, there may be a riser in the combined bathroom. It also needs to be replaced, as do the pipes leading to the neighbors. It is unsafe to leave the old pipeline in the ceiling.

To be replaced at this stage electrical wiring. Having decided on the location of the new lighting fixtures, washing machine, begins new wiring. Replace existing switches and sockets accordingly.

Don't forget about the audit ventilation system. If necessary, it is repaired. The best option counts coercive system ventilation.

The ventilation equipment market includes sufficient quantity models with a variety technical parameters. Knowing the operating features of the bathroom and its area, it is not difficult to calculate what should be specifications purchased fan and air ducts.

Working with walls, floors and ceilings

Depending on the condition of the surfaces, the scale of work may vary. If the walls are uneven, plastering and puttying will be required. Self-execution These procedures are possible with basic skills.

A major renovation of the walls, floor and ceiling will take some time, so you will have to decide on an alternative to the room being renovated.

Facing

Finishing includes painting, laying tiles, covering surfaces with certain mixtures and other work. The ceiling can be covered emulsion paint, choosing the desired shade.

An option with plastic will be practical and easy to maintain. finishing panels. Construction stores offer a huge selection of these decorative elements.

Cost savings are possible if the lower part of the bathtub is covered with a decorative shield. In this case, it is not necessary to lay a tile under it.

Plumbing installation

All plumbing is installed only after completion finishing works, since there is a high risk of equipment damage. In addition, having a bathtub and toilet in the room will make it difficult to access certain areas, preventing them from being properly finished.

Installation of doors and other accessories

The bathroom renovation will be completed by installing furniture (shelves, cabinets) and placing accessories (mirrors, towel hooks, lighting fixtures).


Installation of the front door is carried out at the very last moment. Doing this in advance means creating the risk of damage to the canvas during all the work discussed above.

Having received a sufficient amount of knowledge about how to renovate a bathroom, you can safely get down to business. The result will not be long in coming, and the one who has gained the new kind the bathroom will delight you with its appearance every day.